PSM-II Practice Questions Ppt & Valid PSM-II Exam Cram Pdf - Scrum PSM-II Reliable Exam Cram - Omgzlook

Our PSM-II Practice Questions Ppt exam dumps are required because people want to get succeed in IT field by clearing the certification exam. Passing PSM-II Practice Questions Ppt practice exam is not so easy and need to spend much time to prepare the training materials, that's the reason that so many people need professional advice for PSM-II Practice Questions Ppt exam prep. The PSM-II Practice Questions Ppt dumps pdf are the best guide for them passing test. If you have any questions about Professional Scrum Master level II (PSM II) test torrent or there are any problems existing in the process of the refund you can contact us by mails or contact our online customer service personnel and we will reply and solve your doubts or questions promptly. We guarantee to you that we provide the best PSM-II Practice Questions Ppt study torrent to you and you can pass the exam with high possibility and also guarantee to you that if you fail in the exam unfortunately we will provide the fast and simple refund procedures. The way to pass the PSM-II Practice Questions Ppt actual test is diverse.

Professional Scrum Master PSM-II It is so cool even to think about it.

And you are lucky to find us for we are the most popular vendor in this career and have a strong strength on providing the best PSM-II - Professional Scrum Master level II (PSM II) Practice Questions Ppt study materials. The best part of Pass PSM-II Test exam dumps are their relevance, comprehensiveness and precision. You need not to try any other source forPass PSM-II Test exam preparation.

We have helped tens of thousands of our customers achieve their certification with our excellent PSM-II Practice Questions Ppt exam braindumps. You can see the recruitment on the Internet, and the requirements for PSM-II Practice Questions Ppt certification are getting higher and higher. As the old saying goes, skills will never be burden.

You final purpose is to get the Scrum PSM-II Practice Questions Ppt certificate.

For a long time, high quality is our PSM-II Practice Questions Ppt exam questions constantly attract students to participate in the use of important factors, only the guarantee of high quality, to provide students with a better teaching method, and at the same time the PSM-II Practice Questions Ppt practice quiz brings more outstanding teaching effect. Our high-quality PSM-II Practice Questions Ppt} learning guide help the students know how to choose suitable for their own learning method, our PSM-II Practice Questions Ppt study materials are a very good option.

As is known to us, there are best sale and after-sale service of the PSM-II Practice Questions Ppt certification training dumps all over the world in our company. Our company has employed a lot of excellent experts and professors in the field in the past years, in order to design the best and most suitable PSM-II Practice Questions Ppt latest questions for all customers.

PSM-II PDF DEMO:

QUESTION NO: 1
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C

QUESTION NO: 2
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 3
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C

QUESTION NO: 4
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 5
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

You can effortlessly yield the printouts of Network Appliance NS0-521 exam study material as well, PDF files make it extremely simple for you to switch to any topics with a click. HP HPE7-A01 - As is known to us, where there is a will, there is a way. Moreover, doing these practice tests will impart you knowledge of the actual VMware 3V0-21.23 exam format and develop your command over it. SAP C-HRHFC-2405 - Life is a long journey. Microsoft AZ-700 - Our Professional Scrum Master level II (PSM II) exam prep has taken up a large part of market.