CIMAPRO15-P01-X1-ENG Test Duration & Cima Certification CIMAPRO15-P01-X1-ENG Cost - P1 Management Accounting Question Tutorial - Omgzlook

Do you want to find a job that really fulfills your ambitions? That's because you haven't found an opportunity to improve your ability to lay a solid foundation for a good career. Our CIMAPRO15-P01-X1-ENG Test Duration quiz torrent can help you get out of trouble regain confidence and embrace a better life. Our CIMAPRO15-P01-X1-ENG Test Duration exam question can help you learn effectively and ultimately obtain the authority certification of CIMA, which will fully prove your ability and let you stand out in the labor market. So a lot of people long to know the CIMAPRO15-P01-X1-ENG Test Duration study questions in detail. In order to meet the demands of all people, our company has designed the trail version for all customers. In 21st century, every country had entered the period of talent competition, therefore, we must begin to extend our CIMAPRO15-P01-X1-ENG Test Duration personal skills, only by this can we become the pioneer among our competitors.

CIMA Certification CIMAPRO15-P01-X1-ENG And we have become a popular brand in this field.

According to various predispositions of exam candidates, we made three versions of our CIMAPRO15-P01-X1-ENG - P1 - Management Accounting Question Tutorial Test Duration study materials for your reference: the PDF, Software and APP online. For many people, it’s no panic passing the Test CIMAPRO15-P01-X1-ENG Cram exam in a short time. Luckily enough,as a professional company in the field of Test CIMAPRO15-P01-X1-ENG Cram practice questions ,our products will revolutionize the issue.

We guarantee that you can pass the exam at one time even within one week based on practicing our CIMAPRO15-P01-X1-ENG Test Duration exam materials regularly. 98 to 100 percent of former exam candidates have achieved their success by the help of our CIMAPRO15-P01-X1-ENG Test Duration practice questions. And we have been treated as the best friend as our CIMAPRO15-P01-X1-ENG Test Duration training guide can really help and change the condition which our loyal customers are in and give them a better future.

Our CIMA CIMAPRO15-P01-X1-ENG Test Duration actual test guide can give you some help.

Before you decide to buy Omgzlook of CIMA CIMAPRO15-P01-X1-ENG Test Duration exam questions, you will have a free part of the questions and answers as a trial. So that you will know the quality of the Omgzlook of CIMA CIMAPRO15-P01-X1-ENG Test Duration exam training materials. The CIMA CIMAPRO15-P01-X1-ENG Test Duration exam of Omgzlook is the best choice for you.

CIMAPRO15-P01-X1-ENG Test Duration study materials are here waiting for you! With a higher status, your circle of friends will expand.

CIMAPRO15-P01-X1-ENG PDF DEMO:

QUESTION NO: 1
GH manufactures a product using skilled labour and high quality materials. The company operates a standard costing system and a just-in-time (JIT) purchasing and production system. The standard selling price and variable costs for one unit of the product are as follows:
Calculate the following variances for October, taking account of the more detailed information regarding the labour mix:
(i) The total labour efficiency variance
(ii) The total labour mix variance
(iii) The total labour yield variance
Select the correct statements.
A. Labour efficiency variance: $ 88 000 F
B. Labour efficiency variance: $ 78 000 F
C. Labour mix variance: $ 75 000 F
D. Labour efficiency variance: $ 78 000 A
E. Labour mix variance: $ 63 000 A
F. Labour mix variance: $ 66 000 F
G. Labour yield variance: $ 144 000 A
H. Labour efficiency variance: $ 98 000 A
Answer: D,F,G
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-104-17/

QUESTION NO: 2
A company produces trays of pre-prepared meals that are sold to restaurants and food retailers. Three varieties of meals are sold: economy, premium and deluxe.
Discuss the benefits of flexible budgeting for planning and control purposes.
Select all the true statements.
A. The fixed budget however provides more insight into actual performance.
B. A fixed budget will provide meaningful control information when actual activity differs from budget and variable costs are significant.
C. Reporting against a fixed budget tells management nothing about the efficiency of operations.
D. If actual sales revenue is compared to a fixed budget it is possible to tell whether a favourable sales variance is due to an increase in units sold or an increase in sales price.
E. If sales volumes were well above budget, adverse variable cost variances will probably be reported, against the fixed budget, since more variable costs have to be incurred to support the higher level of activity.
F. If a flexible budget is prepared then the budget variances calculated will provide a better indication of performance since actual results will be compared against an appropriate benchmark.
Answer: C,E,F
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-105-3/

QUESTION NO: 3
LM operates a parcel delivery service. Last year its employees delivered 15,120 parcels and travelled 120,960 kilometers. Total costs were $194,400.
LM has estimated that 70% of its total costs are variable with activity and that 60% of these costs vary with the number of parcels and the remainder vary with the distance travelled.
LM is preparing its budget for the forthcoming year using an incremental budgeting approach and has produced the following estimates:
* All costs will be 3% higher than the previous year due to inflation
* Efficiency will remain unchanged
* A total of 18,360 parcels will be delivered and 128,800 kilometers will be travelled.
Calculate the following costs to be included in the forthcoming year's budget:
(i) the total variable costs related to the number of parcels delivered.
(ii) the total variable costs related to the distance travelled.
A. Parcel related cost for next year = $112,118; Distance related costs for next year = $59,699
B. Parcel related cost for next year = $109,118; Distance related costs for next year = $89,699
C. Parcel related cost for next year = $115,306; Distance related costs for next year = $31,590
D. Parcel related cost for next year = $105,306; Distance related costs for next year = $30,590
E. Parcel related cost for next year = $112,308; Distance related costs for next year = $79,590
Answer: A
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-104-29/

QUESTION NO: 4
A company produces three products D, E and F. The statement below shows the selling price and product costs per unit for each product, based on a traditional absorption costing system.
Each of the products is produced using Process A which has a maximum capacity of 2,500 hours per period.
If a traditional contribution approach is used, the ranking of products, in order of priority, for the profit maximizing product mix will be:
A. F, D, F
B. D, E, F
C. E, D, F
D. D, E, F
Answer: A

QUESTION NO: 5
CH is a building supplies company that sells products to trade and private customers.
Budget data for each of the six months to March are given below:
80% of the value of credit sales is received in the month after sale, 10% two months after sale and 8% three months after sale. The balance is written off as a bad debt.
75% of the value of credit purchases is paid in the month after purchase and the remaining 25% is paid two months after purchase.
All other operating costs are paid in the month they are incurred.
CH has placed an order for four new forklift trucks that will cost $25,000 each. The scheduled payment date is in February.
The cash balance at 1 January is estimated to be $15,000.
Prepare a cash budget for each of the THREE months of January, February and March.
Select All the correct answers.
A. The total receipts in January will be $320 000
B. The total receipts in January will be $245 000
C. The total payments in February will be $405 000
D. Total payments in March will be $323 000
Answer: A,D
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-104-13/

IBM C1000-058 - And the materials we have are very cheap. Microsoft PL-500 - Anyway, after your payment, you can enjoy the one-year free update service with our guarantee. Huawei H12-621_V1.0 - So the choice is important. Besides, the price of our Huawei H13-311_V3.5 learning guide is very favourable even the students can afford it. Omgzlook CIMA Scrum PAL-I exam training materials will be the first step of your achievements.