CIMAPRO15-P01-X1-ENG Questions Fee & Cima Knowledge CIMAPRO15-P01-X1-ENG Points - P1 Management Accounting Question Tutorial - Omgzlook

Are you trying to pass the CIMAPRO15-P01-X1-ENG Questions Fee exam to get the longing CIMAPRO15-P01-X1-ENG Questions Fee certification? As we know, there are a lot of the advantages of the certification, such as higher salaries, better job positions and so on. Perhaps at this moment, you need the help of our CIMAPRO15-P01-X1-ENG Questions Fee study materials. As our company's flagship product, it has successfully helped countless candidates around the world to obtain the coveted CIMAPRO15-P01-X1-ENG Questions Fee certification. If you want to buy our CIMAPRO15-P01-X1-ENG Questions Fee training engine, you must ensure that you have credit card. We do not support deposit card and debit card to pay for the CIMAPRO15-P01-X1-ENG Questions Fee exam questions. For our professional experts simplified the content of theCIMAPRO15-P01-X1-ENG Questions Fee exam questions for all our customers to be understood.

CIMA Certification CIMAPRO15-P01-X1-ENG You can directly print it on papers.

CIMA Certification CIMAPRO15-P01-X1-ENG Questions Fee - P1 - Management Accounting Question Tutorial One of the great advantages of buying our product is that can help you master the core knowledge in the shortest time. If you use our study materials, you must walk in front of the reference staff that does not use valid CIMAPRO15-P01-X1-ENG Latest Exam Camp Pdf real exam. And you will get the according CIMAPRO15-P01-X1-ENG Latest Exam Camp Pdf certification more smoothly.

So, they are reliably rewarding CIMAPRO15-P01-X1-ENG Questions Fee practice materials with high utility value. In compliance with syllabus of the exam, our CIMAPRO15-P01-X1-ENG Questions Fee practice materials are determinant factors giving you assurance of smooth exam. Our CIMAPRO15-P01-X1-ENG Questions Fee practice materials comprise of a number of academic questions for your practice, which are interlinked and helpful for your exam.

CIMA CIMAPRO15-P01-X1-ENG Questions Fee - Omgzlook is a professional website.

We understand your itching desire of the exam. Do not be bemused about the exam. We will satisfy your aspiring goals. Our CIMAPRO15-P01-X1-ENG Questions Fee real questions are high efficient which can help you pass the exam during a week. We just contain all-important points of knowledge into our CIMAPRO15-P01-X1-ENG Questions Fee latest material. And we keep ameliorate our CIMAPRO15-P01-X1-ENG Questions Fee latest material according to requirements of CIMAPRO15-P01-X1-ENG Questions Fee exam. Besides, we arranged our CIMAPRO15-P01-X1-ENG Questions Fee exam prep with clear parts of knowledge. You may wonder whether our CIMAPRO15-P01-X1-ENG Questions Fee real questions are suitable for your current level of knowledge about computer, as a matter of fact, our CIMAPRO15-P01-X1-ENG Questions Fee exam prep applies to exam candidates of different degree. By practicing and remember the points in them, your review preparation will be highly effective and successful.

If you have any questions about the exam, Omgzlook the CIMA CIMAPRO15-P01-X1-ENG Questions Fee will help you to solve them. Within a year, we provide free updates.

CIMAPRO15-P01-X1-ENG PDF DEMO:

QUESTION NO: 1
LM operates a parcel delivery service. Last year its employees delivered 15,120 parcels and travelled 120,960 kilometers. Total costs were $194,400.
LM has estimated that 70% of its total costs are variable with activity and that 60% of these costs vary with the number of parcels and the remainder vary with the distance travelled.
LM is preparing its budget for the forthcoming year using an incremental budgeting approach and has produced the following estimates:
* All costs will be 3% higher than the previous year due to inflation
* Efficiency will remain unchanged
* A total of 18,360 parcels will be delivered and 128,800 kilometers will be travelled.
Calculate the following costs to be included in the forthcoming year's budget:
(i) the total variable costs related to the number of parcels delivered.
(ii) the total variable costs related to the distance travelled.
A. Parcel related cost for next year = $112,118; Distance related costs for next year = $59,699
B. Parcel related cost for next year = $109,118; Distance related costs for next year = $89,699
C. Parcel related cost for next year = $115,306; Distance related costs for next year = $31,590
D. Parcel related cost for next year = $105,306; Distance related costs for next year = $30,590
E. Parcel related cost for next year = $112,308; Distance related costs for next year = $79,590
Answer: A
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-104-29/

QUESTION NO: 2
A company produces three products D, E and F. The statement below shows the selling price and product costs per unit for each product, based on a traditional absorption costing system.
Each of the products is produced using Process A which has a maximum capacity of 2,500 hours per period.
If a traditional contribution approach is used, the ranking of products, in order of priority, for the profit maximizing product mix will be:
A. F, D, F
B. D, E, F
C. E, D, F
D. D, E, F
Answer: A

QUESTION NO: 3
A company produces trays of pre-prepared meals that are sold to restaurants and food retailers. Three varieties of meals are sold: economy, premium and deluxe.
Discuss the benefits of flexible budgeting for planning and control purposes.
Select all the true statements.
A. The fixed budget however provides more insight into actual performance.
B. A fixed budget will provide meaningful control information when actual activity differs from budget and variable costs are significant.
C. Reporting against a fixed budget tells management nothing about the efficiency of operations.
D. If actual sales revenue is compared to a fixed budget it is possible to tell whether a favourable sales variance is due to an increase in units sold or an increase in sales price.
E. If sales volumes were well above budget, adverse variable cost variances will probably be reported, against the fixed budget, since more variable costs have to be incurred to support the higher level of activity.
F. If a flexible budget is prepared then the budget variances calculated will provide a better indication of performance since actual results will be compared against an appropriate benchmark.
Answer: C,E,F
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-105-3/

QUESTION NO: 4
CH is a building supplies company that sells products to trade and private customers.
Budget data for each of the six months to March are given below:
80% of the value of credit sales is received in the month after sale, 10% two months after sale and 8% three months after sale. The balance is written off as a bad debt.
75% of the value of credit purchases is paid in the month after purchase and the remaining 25% is paid two months after purchase.
All other operating costs are paid in the month they are incurred.
CH has placed an order for four new forklift trucks that will cost $25,000 each. The scheduled payment date is in February.
The cash balance at 1 January is estimated to be $15,000.
Prepare a cash budget for each of the THREE months of January, February and March.
Select All the correct answers.
A. The total receipts in January will be $320 000
B. The total receipts in January will be $245 000
C. The total payments in February will be $405 000
D. Total payments in March will be $323 000
Answer: A,D
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-104-13/

QUESTION NO: 5
GH manufactures a product using skilled labour and high quality materials. The company operates a standard costing system and a just-in-time (JIT) purchasing and production system. The standard selling price and variable costs for one unit of the product are as follows:
Calculate the following variances for October, taking account of the more detailed information regarding the labour mix:
(i) The total labour efficiency variance
(ii) The total labour mix variance
(iii) The total labour yield variance
Select the correct statements.
A. Labour efficiency variance: $ 88 000 F
B. Labour efficiency variance: $ 78 000 F
C. Labour mix variance: $ 75 000 F
D. Labour efficiency variance: $ 78 000 A
E. Labour mix variance: $ 63 000 A
F. Labour mix variance: $ 66 000 F
G. Labour yield variance: $ 144 000 A
H. Labour efficiency variance: $ 98 000 A
Answer: D,F,G
Explanation/Reference: https://www.vrelearnonline.com/cima-p1-104-17/

Considering many exam candidates are in a state of anguished mood to prepare for the VMware 5V0-92.22 exam, our company made three versions of VMware 5V0-92.22 real exam materials to offer help. The effect of Omgzlook's CIMA SAP C_SAC_2415 exam training materials is reflected particularly good by the use of the many candidates. Cisco 300-540 - The world today is in an era dominated by knowledge. If you are still study hard to prepare the CIMA Oracle 1Z0-819 exam, you're wrong. Even if you have no basic knowledge about the relevant knowledge, you still can pass the EMC D-CSF-SC-23 exam.

Updated: May 27, 2022