CTAL-TM_Syll2012 Learning Material - Isqi New ISTQB Certified Tester Advanced Level Test Manager [Syllabus 2012] Test Questions Fee - Omgzlook

The free demos give you a prove-evident and educated guess about the content of our CTAL-TM_Syll2012 Learning Material practice questions. As long as you make up your mind on this CTAL-TM_Syll2012 Learning Material exam, you can realize their profession is unquestionable. And you will be surprised to find the high-quality of our CTAL-TM_Syll2012 Learning Material exam braindumps. Though the content of these three versions is the same, the displays have their different advantages. With our CTAL-TM_Syll2012 Learning Material study materials, you can have different and pleasure study experience as well as pass CTAL-TM_Syll2012 Learning Material exam easily. We believe that you will like our products.

ISQI Certifications CTAL-TM_Syll2012 They are free demos.

On the one hand, our company hired the top experts in each qualification examination field to write the CTAL-TM_Syll2012 - ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] Learning Material prepare dump, so as to ensure that our products have a very high quality, so that users can rest assured that the use of our research materials. When we choose the employment work, you will meet a bottleneck, how to let a company to choose you to be a part of him? We would say ability, so how does that show up? There seems to be only one quantifiable standard to help us get a more competitive job, which is to get the test CTAL-TM_Syll2012 Valid Exam Camp Pdfcertification and obtain a qualification. If you want to have a good employment platform, then take office at the same time there is a great place to find that we have to pay attention to the importance of qualification examination.

You will get a better job or get a big rise on the position as well as the salary. And we can claim that if you study with our CTAL-TM_Syll2012 Learning Material study materials for 20 to 30 hours, you will pass the exam with ease. Perhaps you do not understand.

ISQI CTAL-TM_Syll2012 Learning Material - It absolutely has no problem.

At the fork in the road, we always face many choices. When we choose job, job are also choosing us. Today's era is a time of fierce competition. Our CTAL-TM_Syll2012 Learning Material exam question can make you stand out in the competition. Why is that? The answer is that you get the certificate. What certificate? Certificates are certifying that you have passed various qualifying examinations. Watch carefully you will find that more and more people are willing to invest time and energy on the CTAL-TM_Syll2012 Learning Material exam, because the exam is not achieved overnight, so many people are trying to find a suitable way.

What is more, there are extra place for you to make notes below every question of the CTAL-TM_Syll2012 Learning Material practice quiz. Don't you think it is quite amazing? Just come and have a try!

CTAL-TM_Syll2012 PDF DEMO:

QUESTION NO: 1
You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell special packages in their wine shops.
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the system testinG.
EXCR1- Each "critical" quality risk item must be covered by at least one test condition
EXCR2- Each "critical" requirement must be covered by at least one test condition
The following are the "critical" requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time
REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles,
6-bottles, 12-bottles, 15-bottles)
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and no more bottles than the package size. No error messages shall be displayed if the user selects a valid number of bottles (at least 1 bottle and no more than the package size)
REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid number of bottles is selected by the user (zero bottles or a number higher than the package size)
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa,
MasterCard, American Express)
REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card data are given by the user
The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user Test analysis for system testing has just begun and the following test conditions have been identified.
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
K3 2 credits
A. 4
B. 3
C. 2
D. 1
Answer: A

QUESTION NO: 2
The following are the requirements identified as "critical":
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the
"select" and "purchase" pages going back to the "browse" page (anonymous navigation)
Moreover the following quality risk item has been identified as "critical":
QR-P1. The web customer portal might not be able to provide the expected response time (less than
10 sec) for the purchase transactions under a load of up-to 1000 concurrent users
Test analysis for system testing has just begun and the following test conditions have been identifieD.
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
K3 2 credits
A. 1
B. 2
C. 3
D. 4
Answer: C

QUESTION NO: 3
You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell special packages in their wine shops.
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the system testinG. EXCR1- Each "critical" quality risk item must be covered by at least one test condition EXCR2- Each "critical" requirement must be covered by at least one test condition
The following are the "critical" requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time
REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles,
6-bottles, 12-bottles, 15-bottles)
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and no more bottles than the package size. No error messages shall be displayed if the user selects a valid number of bottles (at least 1 bottle and no more than the package size)
REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid number of bottles is selected by the user (zero bottles or a number higher than the package size)
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa,
MasterCard, American Express)
REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card data are given by the user
QUSTION NO: 11 The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been identifieD.
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user
Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete and correct, and covers the
REQSEL-4 requirement?
K3 2 credits
A. Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed
B. Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed
C. Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed
D. Select a 6-bottles package, then try to insert 7 bottles
Answer: C

QUESTION NO: 4
Which of the following is an example of the test closure activity indicated as "lessons learned"?
K2 1 credit
A. Archive all the test results of the acceptance testing phase
B. Deliver a list of the open defects of a software product released into production to the service desk team
C. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
D. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing
Answer: C

QUESTION NO: 5
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
K2 1 credit
A. A traceability matrix showing the relationships between the product risk items and the test cases
B. A list of all the open defects with the associated classification information extracted from the defect tracking system
C. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system
D. The execution status of all the test cases extracted from the test management tool
Answer: C

EMC D-PSC-MN-01 - First, we have high pass rate as 98% to 100% which is unique in the market. And if you don't know which one to buy, you can free download the demos of the HP HPE7-A01 study materials to check it out. Our company has established a long-term partnership with those who have purchased our Oracle 1z0-1127-24 exam guides. We believe that the SAP C-TS422-2023 exam questions from our company will help all customers save a lot of installation troubles. Network Appliance NS0-528 practice quiz provide you with the most realistic test environment, so that you can adapt in advance so that you can easily deal with formal exams.