1Z0-1057 Latest Test Questions And Answers & Oracle Vce 1Z0-1057 Files - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials - Omgzlook

The quality of Omgzlook product is very good and also have the fastest update rate. If you purchase the training materials we provide, you can pass Oracle certification 1Z0-1057 Latest Test Questions And Answers exam successfully. We are keeping advancing with you. You will regret if you do not choose our study materials. Omgzlook can help you 100% pass Oracle certification 1Z0-1057 Latest Test Questions And Answers exam, and if you carelessly fail to pass Oracle certification 1Z0-1057 Latest Test Questions And Answers exam, we will guarantee a full refund for you.

Oracle Project Portfolio Management Cloud 1Z0-1057 In this, you can check its quality for yourself.

We always accept feedbacks from users, and take many of the good recommendations, resulting in a perfect Omgzlook Oracle 1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Latest Test Questions And Answers exam materials. Our target is to reduce your pressure and improve your learning efficiency from preparing for 1Z0-1057 Latest Practice Questions exam. If you still worry about your 1Z0-1057 Latest Practice Questions exam; if you still doubt whether it is worthy of purchasing our software, what you can do to clarify your doubts is to download our 1Z0-1057 Latest Practice Questions free demo.

Training materials of Omgzlook are currently the most popular materials on the internet. 1Z0-1057 Latest Test Questions And Answers Exam is a milestone in your career. In this competitive world, it is more important than ever.

Oracle 1Z0-1057 Latest Test Questions And Answers - PDF version is easy for read and print out.

Omgzlook is a reliable site offering the 1Z0-1057 Latest Test Questions And Answers valid study material supported by 100% pass rate and full money back guarantee. Besides, our 1Z0-1057 Latest Test Questions And Answers training material is with the high quality and can simulate the actual test environment, which make you feel in the real test situation. You can get the latest information about the 1Z0-1057 Latest Test Questions And Answers real test, because our Omgzlook will give you one year free update. You can be confident to face any difficulties in the 1Z0-1057 Latest Test Questions And Answers actual test no matter any changes.

Once you have well prepared with our 1Z0-1057 Latest Test Questions And Answers dumps collection, you will go through the formal test without any difficulty. To help people pass exam easily, we bring you the latest 1Z0-1057 Latest Test Questions And Answers exam prep for the actual test which enable you get high passing score easily in test.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

QUESTION NO: 2
Which three tools are available for accessing REST APIs?
A. Web Browser
B. Oracle Transactional Business Intelligence
C. Programming Language
D. cURL
Answer: A,C,D
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/18b/fapap/Use_cURL.html REST API = REpresentational State nterface (API)

QUESTION NO: 3
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 4
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 5
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)
A. The US and UK business units are linked to different ledgers than the China business unit.
B. The China business unit is associated with a different legal entity than the US and UK business units.
C. The project accountant is not assigned to the external role that grants access to the China business unit.
D. The application role relevant to the China business unit is not assigned to the project accountant.
Answer: C

Our website aimed to help you to get through your certification test easier with the help of our valid Microsoft AZ-104 vce braindumps. You can find all the key points in the Oracle 1z0-1042-24 practice torrent. Cisco 700-245 - SWREG will cost extra tax such as intellectual property taxation. You can get prepared with our SAP C_DBADM_2404 exam materials only for 20 to 30 hours before you go to attend your exam. About the updated Oracle study material, our system will send the latest one to your payment email automatically as soon as the EMC D-ZT-DS-P-23 updated.