Nowadays the requirements for jobs are higher than any time in the past. The job-hunters face huge pressure because most jobs require both working abilities and profound major knowledge. Passing 1Z1-1057 Latest Exam Camp File exam can help you find the ideal job. Because Omgzlook exam dumps contain all questions you can encounter in the actual exam, all you need to do is to memorize these questions and answers which can help you 100% pass the exam. This is the royal road to pass 1Z1-1057 Latest Exam Camp File exam. However, our 1Z1-1057 Latest Exam Camp File training materials can offer better condition than traditional practice materials and can be used effectively.

Oracle Project Portfolio Management Cloud 1Z1-1057 If you fail, don't forget to learn your lesson.

So the PDF version of our 1Z1-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Latest Exam Camp File exam questions is convenient. Don't hesitate to get help from our customer assisting. Downloading the New 1Z1-1057 Test Study Guide free demo doesn't cost you anything and you will learn about the pattern of our practice exam and the accuracy of our New 1Z1-1057 Test Study Guide test answers.

We often ask, what is the purpose of learning? Why should we study? Why did you study for 1Z1-1057 Latest Exam Camp Fileexam so long? As many people think that, even if one day we forget the formula for the area of a triangle, we can still live very well, but if it were not for the knowledge of learning 1Z1-1057 Latest Exam Camp File exam and try to obtain certification, how can we have the opportunity to good to future life? So, the examination is necessary, only to get the test 1Z1-1057 Latest Exam Camp File certification, get a certificate, to prove better us, to pave the way for our future life.

Oracle 1Z1-1057 Latest Exam Camp File - Also, your normal life will not be disrupted.

Discount is being provided to the customer for the entire Oracle 1Z1-1057 Latest Exam Camp File preparation suite. These 1Z1-1057 Latest Exam Camp File learning materials include the 1Z1-1057 Latest Exam Camp File preparation software & PDF files containing sample Interconnecting Oracle 1Z1-1057 Latest Exam Camp File and answers along with the free 90 days updates and support services. We are facilitating the customers for the Oracle 1Z1-1057 Latest Exam Camp File preparation with the advanced preparatory tools.

It is also known to us that passing the exam is not an easy thing for many people, so a good study method is very important for a lot of people, in addition, a suitable study tool is equally important, because the good and suitable 1Z1-1057 Latest Exam Camp File reference guide can help people pass the exam in a relaxed state. We are glad to introduce the 1Z1-1057 Latest Exam Camp File certification dumps from our company to you.

1Z1-1057 PDF DEMO:

QUESTION NO: 1
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 2
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset

QUESTION NO: 3
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 4
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

QUESTION NO: 5
Which three tools are available for accessing REST APIs?
A. Web Browser
B. Oracle Transactional Business Intelligence
C. Programming Language
D. cURL
Answer: A,C,D
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/18b/fapap/Use_cURL.html REST API = REpresentational State nterface (API)

I believe that after you try CheckPoint 156-521 training engine, you will love them. We can make sure that the PDF version of the IIA IIA-CHAL-QISA test questions will be very convenient for all people. Cisco 200-301 - Omgzlook's experts have simplified the complex concepts and have added examples, simulations and graphs to explain whatever could be difficult for you to understand. Microsoft MB-500 - For a long time, our company is insisting on giving back to our customers. More about Fortinet NSE7_NST-7.2 Exams Dumps: If you want to know more about our test preparations materials, you should explore the related Fortinet NSE7_NST-7.2 exam Page.