1Z0-1057 Valid Exam Review - New Exam 1Z0-1057 Braindumps & Oracle Project Portfolio Management Cloud 2019 Implementation Essentials - Omgzlook

Are you racking your brains for a method how to pass Oracle 1Z0-1057 Valid Exam Review exam? Oracle 1Z0-1057 Valid Exam Review certification test is one of the valuable certification in modern IT certification. Within the last few decades, IT got a lot of publicity and it has been a necessary and desirable part of modern life. Oracle certification has been well recognized by international community. Our training program can effectively help you have a good preparation for Oracle certification 1Z0-1057 Valid Exam Review exam. Omgzlook's training program will be your best choice. If you don't believe what I say, you can know the information by asking around.

Oracle Project Portfolio Management Cloud 1Z0-1057 There are two versions of Omgzlook dumps.

In order to meet the request of current real test, the technology team of research on Omgzlook Oracle 1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Valid Exam Review exam materials is always update the questions and answers in time. Once you have checked our demo, you will find the study materials we provide are what you want most. Our target is to reduce your pressure and improve your learning efficiency from preparing for 1Z0-1057 Reliable Exam Preparation exam.

This is really worth the price, the value it creates is far greater than the price. If your budget is limited, but you need complete exam material. Then you can try the Omgzlook's Oracle 1Z0-1057 Valid Exam Review exam training materials.

Oracle 1Z0-1057 Valid Exam Review - Our strength will make you incredible.

The secret that Omgzlook helps many candidates pass 1Z0-1057 Valid Exam Review exam is Oracle exam questions attentively studied by our professional IT team for years, and the detailed answer analysis. We constantly updated the 1Z0-1057 Valid Exam Review exam materials at the same time with the exam update. We try our best to ensure 100% pass rate for you.

The opportunity always belongs to a person who has the preparation. But, when opportunities arise, will you seize the opportunities successfully? At present, you are preparing for Oracle 1Z0-1057 Valid Exam Review test.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 2
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 3
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

QUESTION NO: 4
Which three tools are available for accessing REST APIs?
A. Web Browser
B. Oracle Transactional Business Intelligence
C. Programming Language
D. cURL
Answer: A,C,D
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/18b/fapap/Use_cURL.html REST API = REpresentational State nterface (API)

QUESTION NO: 5
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset

ARDMS SPI - So our Omgzlook will provide a exam simulation for you to experience the real exam model before real exam. And with the aid of Huawei H11-851_V4.0 certification test, you can improve your skills and master some useful techniques in your job so that you can finish your work better and demonstrate your great ability before other people. Also you can ask us any questions about SAP C_THR83_2405 exam any time as you like. Have you learned Omgzlook Oracle EMC D-PDD-OE-23 exam dumps? Why do the people that have used Omgzlook dumps sing its praises? Do you really want to try it whether it have that so effective? Hurry to click Omgzlook to download our certification training materials. SAP C_LIXEA_2404 study guide is the best product to help you achieve your goal.