1Z0-1057 Learning Cram - Oracle New Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Test Cram - Omgzlook

Omgzlook is able to let you need to spend less time, money and effort to prepare for Oracle certification 1Z0-1057 Learning Cram exam, which will offer you a targeted training. You only need about 20 hours training to pass the exam successfully. Oracle certification 1Z0-1057 Learning Cram exam is a test of IT professional knowledge. What you will never worry about is that the quality of 1Z0-1057 Learning Cram exam dumps, because once you haven’t passed exam, we will have a 100% money back guarantee. You can easily pass the exam only if you spend some spare time studying our 1Z0-1057 Learning Cram materials. Oracle 1Z0-1057 Learning Cram authentication certificate is the dream IT certificate of many people.

Oracle Project Portfolio Management Cloud 1Z0-1057 So Omgzlook a website worthy of your trust.

Oracle Project Portfolio Management Cloud 1Z0-1057 Learning Cram - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials The high pass rate of our study materials means that our products are very effective and useful for all people to pass their exam and get the related certification. Do not spend too much time and money, as long as you have Omgzlook learning materials you will easily pass the exam. In order to help you more Omgzlook the Oracle Latest 1Z0-1057 Dumps Ebook exam eliminate tension of the candidates on the Internet.

Be supportive to offline exercise on the condition that you practice it without mobile data. According to personal propensity and various understanding level of exam candidates, we have three versions of 1Z0-1057 Learning Cram practice materials for your reference. Here are the respective features and detailed disparities of our 1Z0-1057 Learning Cram practice materials.

Oracle 1Z0-1057 Learning Cram - You can experience it in advance.

In order to meet the request of current real test, the technology team of research on Omgzlook Oracle 1Z0-1057 Learning Cram exam materials is always update the questions and answers in time. We always accept feedbacks from users, and take many of the good recommendations, resulting in a perfect Omgzlook Oracle 1Z0-1057 Learning Cram exam materials. This allows Omgzlook to always have the materials of highest quality.

If you still worry about your 1Z0-1057 Learning Cram exam; if you still doubt whether it is worthy of purchasing our software, what you can do to clarify your doubts is to download our 1Z0-1057 Learning Cram free demo. Once you have checked our demo, you will find the study materials we provide are what you want most.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

QUESTION NO: 2
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 3
Which three tools are available for accessing REST APIs?
A. Web Browser
B. Oracle Transactional Business Intelligence
C. Programming Language
D. cURL
Answer: A,C,D
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/18b/fapap/Use_cURL.html REST API = REpresentational State nterface (API)

QUESTION NO: 4
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 5
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)
A. The US and UK business units are linked to different ledgers than the China business unit.
B. The China business unit is associated with a different legal entity than the US and UK business units.
C. The project accountant is not assigned to the external role that grants access to the China business unit.
D. The application role relevant to the China business unit is not assigned to the project accountant.
Answer: C

EMC D-VXR-OE-23 - This certification exam can also help you tap into many new avenues and opportunities. Our Dell D-AX-DY-A-00 exam software is developed by our IT elite through analyzing real Dell D-AX-DY-A-00 exam content for years, and there are three version including PDF version, online version and software version for you to choose. Do you want to pass the Oracle SAP C-S4FCF-2023 exam better and faster? Then please select the Omgzlook. We constantly updated the Microsoft DP-100 exam materials at the same time with the exam update. Will you seize Omgzlook to make you achievement? Omgzlook Oracle Dell D-HCIAZ-A-01 certification training materials will guarantee your success.