1Z0-1057 Exam - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Valid Test Pattern - Omgzlook

In order to cater to the different needs of people from different countries in the international market, we have prepared three kinds of versions of our 1Z0-1057 Exam learning questions in this website. And we can assure you that you will get the latest version of our 1Z0-1057 Exam training materials for free from our company in the whole year after payment on 1Z0-1057 Exam practice quiz. Last but not least, we will provide the most considerate after sale service for our customers on our 1Z0-1057 Exam exam dumps. They have more competitiveness among fellow workers and are easier to be appreciated by their boss. In fact, the users of our 1Z0-1057 Exam exam have won more than that, but a perpetual wealth of life. We can say that our 1Z0-1057 Exam test questions are the most suitable for examinee to pass the exam, you will never regret to buy it.

Oracle Project Portfolio Management Cloud 1Z0-1057 The experts will update the system every day.

What are you waiting for? Come and buy 1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Exam study guide now! Our 1Z0-1057 Exam Objectives Pdf study guide design three different versions for all customers. These three different versions include PDF version, software version and online version, they can help customers solve any problems in use, meet all their needs.

For most users, access to the relevant qualifying examinations may be the first, so many of the course content related to qualifying examinations are complex and arcane. According to these ignorant beginners, the 1Z0-1057 Exam exam questions set up a series of basic course, by easy to read, with corresponding examples to explain at the same time, the Oracle Project Portfolio Management Cloud 2019 Implementation Essentials study question let the user to be able to find in real life and corresponds to the actual use of learned knowledge, deepened the understanding of the users and memory. Simple text messages, deserve to go up colorful stories and pictures beauty, make the 1Z0-1057 Exam test guide better meet the zero basis for beginners, let them in the relaxed happy atmosphere to learn more useful knowledge, more good combined with practical, so as to achieve the state of unity.

Oracle 1Z0-1057 Exam - Now they have a better life.

If we waste a little bit of time, we will miss a lot of opportunities. If we miss the opportunity, we will accomplish nothing. Then, life becomes meaningless. Our 1Z0-1057 Exam preparation exam have taken this into account, so in order to save our customer’s precious time, the experts in our company did everything they could to prepare our 1Z0-1057 Exam study materials for those who need to improve themselves quickly in a short time to pass the exam to get the 1Z0-1057 Exam certification.

If you are agonizing about how to pass the exam and to get the Oracle certificate, now you can try our learning materials. Our reputation is earned by high-quality of our learning materials.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit. Why is he not able to see the transactions for the China business unit? (Choose the best answer.)
A. The US and UK business units are linked to different ledgers than the China business unit.
B. The China business unit is associated with a different legal entity than the US and UK business units.
C. The project accountant is not assigned to the external role that grants access to the China business unit.
D. The application role relevant to the China business unit is not assigned to the project accountant.
Answer: C

QUESTION NO: 2
Which three tools are available for accessing REST APIs?
A. Web Browser
B. Oracle Transactional Business Intelligence
C. Programming Language
D. cURL
Answer: A,C,D
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/18b/fapap/Use_cURL.html REST API = REpresentational State nterface (API)

QUESTION NO: 3
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

QUESTION NO: 4
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)
A. Accounting date is the first day of the first open accounting period.
B. Project accounting date is the first day of the first open project accounting period.
C. Accounting date is the same as the original invoice date.
D. Project accounting date is the same as the original invoice date.
E. Project accounting date is the last day of the open project accounting period.
Answer: A,D

QUESTION NO: 5
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

The questions and answers of our SAP C-HRHPC-2405 exam questions are refined and have simplified the most important information so as to let the clients use little time to learn. The staff of CheckPoint 156-587 study materials is online 24 hours a day, seven days a week. So our study materials are helpful to your preparation of the Amazon SAA-C03 exam. Netskope NSK101 - So we have advandages not only on the content but also on the displays. Amazon DOP-C02 - In the end, you will become an excellent talent.