E20-011 Valid Exam Sample Questions - Emc E20-011 New App Simulations & Storage Networking Design And Management - Omgzlook

And after you finish the E20-011 Valid Exam Sample Questions exam questions, the scores will show out right away. Our system will accurately help you analyze the exercises of the E20-011 Valid Exam Sample Questions study materials. So you need not to summarize by yourself. To help you pass the E20-011 Valid Exam Sample Questions exam is our goal. The close to 100% passing rate of our dumps allow you to be rest assured in our products. I have confidence in our Omgzlook products that soon Omgzlook's exam questions and answers about EMC E20-011 Valid Exam Sample Questions will be your choice and you will pass EMC certification E20-011 Valid Exam Sample Questions exam successfully.

We have the complete list of popular E20-011 Valid Exam Sample Questions exams.

Actually, E20-011 - Storage Networking Design and Management Valid Exam Sample Questions exam really make you anxious. After our unremitting efforts, E20-011 Certification Questions learning guide comes in everybody's expectation. Our professional experts not only have simplified the content and grasp the key points for our customers, but also recompiled the E20-011 Certification Questions preparation materials into simple language so that all of our customers can understand easily no matter which countries they are from.

Every version of E20-011 Valid Exam Sample Questions study materials that we provide to you has its own advantage: the PDF version has no equipment limited, which can be read anywhere; the online version can use on any electronic equipment there is network available; the software version can simulate the real E20-011 Valid Exam Sample Questions exam environment to let you have more real feeling to E20-011 Valid Exam Sample Questions real exam, besides the software version can be available installed on unlimited number devices.

EMC E20-011 Valid Exam Sample Questions - You can study any time anywhere you want.

We guarantee that after purchasing our E20-011 Valid Exam Sample Questions exam torrent, we will deliver the product to you as soon as possible within ten minutes. So you don’t need to wait for a long time and worry about the delivery time or any delay. We will transfer our Storage Networking Design and Management prep torrent to you online immediately, and this service is also the reason why our E20-011 Valid Exam Sample Questions test braindumps can win people’s heart and mind. Therefore, you are able to get hang of the essential points in a shorter time compared to those who are not willing to use our E20-011 Valid Exam Sample Questions exam torrent.

The most important is that our test engine enables you practice E20-011 Valid Exam Sample Questions exam pdf on the exact pattern of the actual exam. Our IT professionals have made their best efforts to offer you the latest E20-011 Valid Exam Sample Questions study guide in a smart way for the certification exam preparation.

E20-011 PDF DEMO:

QUESTION NO: 1
A company must decide whether to introduce a new product line. The new product will have startup costs, operational costs, and incoming cash flows over 5 years. This project will have an immediate (T=0) cash outflow of $100,000 that may include machinery and employee training costs. Other cash outflows for years 1-5 are expected to be $5,000 per year. Cash inflows are expected to be $30,000 per year for years 1-5. The required rate of return is 10 percent. The present value (PV) can be calculated for each year: T=0 -$100,000 / 1.100 = -$100,000 PV T=1 ($30,000 - $5,000)/ 1.101 = $22,727 PV T=2 ($30,000
- $5,000)/ 1.102 = $20,661 PV T=3 ($30,000 - $5,000)/ 1.103 = $18,783 PV T=4 ($30,000 - $5,000)/
1.104 = $17,075 PV T=5 ($30,000 - $5,000)/ 1.105 = $15,523 PV What is the recommendation to the company?
A. The company should invest in the project since it will gain $125,000 in profit.
B. The company should not invest in the project. It will not see any gain from the investment.
C. The project will break even and it should not be considered.
D. The project will break even and should be considered.
Answer: B

QUESTION NO: 2
Click the Exhibit button.
The chart shows the Net Present Value (NPV) of $50,000 in 5 years, with a discount rate of 10% each year. The company invests $98,000 on new monitoring software for its critical database. An annual yield of $50,000 is expected. What is the first time the company will see its investment yielding positive returns?
A. Year 2
B. Year 3
C. Year 4
D. Year 5
Answer: B

QUESTION NO: 3
The results of an SRM Implementation Study are:
1. Software license costs: $150,000
2. Software customization and installation: $50,000 The current projection of a new storage hardware requirement over the next 5 years is estimated at 85 TB. SRM implementation will reduce the storage requirements to 55 TB. The cost of storage is $50,000 per TB. The 3-year total cost of ownership (TCO) without SRM implementation = 85*(50,000) The 3-year total cost of ownership (TCO) with SRM implementation = 150,000 + 50,000 + 55*(50,000) What is the return on investment (ROI) with the SRM implementation?
A. 6.5%
B. 65%
C. 650%
D. 6,500%
Answer: B

QUESTION NO: 4
A 200 GB database is currently hosted on an enterprise storage subsystem. The application requires three point-in-time copies to be presented to three other hosts that perform different types of reporting on the database. A pointer-based point-in-time copy is estimated to use 25% of the original capacity per copy of the database. What is the additional storage demand this application has generated to meet the requirement?
A. 75 GB
B. 150 GB
C. 200 GB
D. 600 GB
Answer: B

QUESTION NO: 5
Click the Exhibit button.
Areas A, B, and C are three performance segments that represent demands of application classes. What are the predominant performance characteristics in segments A, B, and C?
A. A=Availability; B=Throughput; C=Ease of Management
B. A=Ease of Management; B=Availability; C=Throughput
C. A=Ease of Management; B=Throughput; C=Availability
D. A=Throughput; B=Ease of Management; C=Availability
Answer: B

Passing a SAP C-THR85-2405 exam to get a certificate will help you to look for a better job and get a higher salary. Our experts written the accurate Adobe AD0-E906 test answers for exam preparation and created the study guideline for our candidates. You will love our Huawei H12-621_V1.0 exam questions as long as you have a try! We often regard learning for Salesforce CRT-251 exam as a torture. Appian ACA100 - And they are the masterpieces of processional expertise these area with reasonable prices.