ACP-100 Latest Exam Topics Pdf - ACP-100 Latest Exam Cram Sheet & Jira Administrator Exam - Omgzlook

People are engaged in modern society. So our goal is to achieve the best learning effect in the shortest time. So our ACP-100 Latest Exam Topics Pdf test prep will not occupy too much time. By focusing on how to help you effectively, we encourage exam candidates to buy our ACP-100 Latest Exam Topics Pdf practice test with high passing rate up to 98 to 100 percent all these years. Our ATLASSIAN exam dumps almost cover everything you need to know about the exam. One of the great advantages is that you will soon get a feedback after you finish the exercises.

Jira Administrator ACP-100 We have always advocated customer first.

Our company attaches great importance on improving the ACP-100 - Jira Administrator Exam Latest Exam Topics Pdf study prep. After you use our study materials, you can get Reliable ACP-100 APP Simulations certification, which will better show your ability, among many competitors, you will be very prominent. Using Reliable ACP-100 APP Simulations exam prep is an important step for you to improve your soft power.

This kind of learning method is convenient and suitable for quick pace of life. But you must have a browser on your device. Also, you must open the online engine of the study materials in a network environment for the first time.

ATLASSIAN ACP-100 Latest Exam Topics Pdf - It will be a first step to achieve your dreams.

There may be a lot of people feel that the preparation process for ACP-100 Latest Exam Topics Pdf exams is hard and boring, and hard work does not necessarily mean good results, which is an important reason why many people are afraid of examinations. Today, our ACP-100 Latest Exam Topics Pdf exam materials will radically change this. High question hit rate makes you no longer aimless when preparing for the exam, so you just should review according to the content of our ACP-100 Latest Exam Topics Pdf study guide prepared for you.

So there is nothing to worry about, just buy our ACP-100 Latest Exam Topics Pdf exam questions. It is our consistent aim to serve our customers wholeheartedly.

ACP-100 PDF DEMO:

QUESTION NO: 1
Tom has asked you why the numbers returned by his searches are not right. He shows you three JQL queries:
How can you fix this?
A. Change the query to project = "Cake Baking" and ( fixVersion is empty or fixVersion != 1.1.0 ).
B. Change the query to project = "Cake Baking" and fixVersion ~ 1.1.0.
C. Change the query to project = "Cake Baking" and fixVersion not in (1.1.0).
D. Identify the missing issues and change the permissions so that everyone can see them.
E. Rename the versions so they do not contain periods.
Answer: D

QUESTION NO: 2
You receive workflow configuration requirements for issues in the Closed status. They are as follows:
* Users must NOT be able to edit issues in this status.
* Jira administrators must be able to edit issues in this status.
* Only users in the release-managers group should see the transition to the Re-opened status Which combination of two workflow configuration items should you use to meet these requirements?
(Choose two.)
A. Conditions
B. Triggers
C. Validators
D. Properties
E. Post functions
Answer: A,C

QUESTION NO: 3
You set up a new project for a team. Soon afterward, users report that a field is missing from one of their screens. You check the screen configuration in the administration panel and you see that the field should be present.
Why can't the users see the field?
A. The field context does not include the project and/or issue type.
B. The issue operation wasn't mapped to a screen.
C. The changes to the screen were not published.
D. The users don't have permission to view that field.
Answer: D

QUESTION NO: 4
Your organization has a Jira project for managing work on a software development project.
As the team has grown, two groups have formed within it, working on different tasks. To help bring more focus to the work being conducted, the team has requested a second Jira project to split the team's work into two.
Which set of schemes can likely be shared between the two projects?
A. Workflow and Custom Field
B. Notification and Workflow
C. Issue Type and Sub-task
D. Custom Field and Issue Security
E. Resolution and Notification
Answer: A

QUESTION NO: 5
An issue is showing the Time Tracking section as follows:
There is clearly an hour's difference between the Original and Remaining estimates.
Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)
A. The hour's work was logged via a REST call by the user.
B. Time tracking was not enabled when the work was logged.
C. The original estimate was increased.
D. The remaining estimate was adjusted without logging any effort.
E. You do not have view permission to see the logged work.
F. The work log would have exceeded the project's time allowance, so it cannot be counted.
Answer: B,D

If you still worried about whether or not you pass exam; if you still doubt whether it is worthy of purchasing our software, what can you do to clarify your doubts that is to download free demo of EMC D-PCM-DY-23. You just should take the time to study EMC D-VXB-DY-A-24 preparation materials seriously, no need to refer to other materials, which can fully save your precious time. If you think i'm exaggerating, you might as well take a look at our EMC D-PST-OE-23 actual exam. Though our SAP C_THR92_2405 training guide is proved to have high pass rate, but If you try our SAP C_THR92_2405 exam questions but fail in the final exam, we can refund the fees in full only if you provide us with a transcript or other proof that you failed the exam. SAP C-ARP2P-2404 - The three versions are very flexible for all customers to operate.