CCRA-L2 Certification Test Questions - Aiwmi New Certified Credit Research Analyst Level 2 Test Sample Questions - Omgzlook

Due to the shortage of useful practice materials or being scanty for them, many candidates may choose the bad quality exam materials, but more and more candidates can choose our CCRA-L2 Certification Test Questions study materials. Actually, some practice materials are shooting the breeze about their effectiveness, but our CCRA-L2 Certification Test Questions training quiz are real high quality practice materials with passing rate up to 98 to 100 percent. And you will be amazed to find that our CCRA-L2 Certification Test Questions exam questions are exactly the same ones in the real exam. Opportunities always for those who are well prepared and we wish you not to miss the good opportunities. Omgzlook provide you with the most authoritative and the fullest AIWMI CCRA-L2 Certification Test Questions exam dumps, thus the hit rate is very high. The most important part is that all contents were being sifted with diligent attention.

Now, CCRA-L2 Certification Test Questions exam guide gives you this opportunity.

AIWMI CCRA CCRA-L2 Certification Test Questions - Certified Credit Research Analyst Level 2 The time and energy are all very important for the office workers. About some esoteric points, they illustrate with examples for you on the Latest Test CCRA-L2 Questions Answers exam braindumps. With the cumulative effort over the past years, our Latest Test CCRA-L2 Questions Answers study guide has made great progress with passing rate up to 98 to 100 percent among the market.

In addition, you will instantly download the CCRA-L2 Certification Test Questions pdf vce after you complete the payment. With the help of CCRA-L2 Certification Test Questions study dumps, you can just spend 20-30 hours for the preparation. Then you will be confident in the actual test.

AIWMI CCRA-L2 Certification Test Questions - .

If you want to through the AIWMI CCRA-L2 Certification Test Questions certification exam to make a stronger position in today's competitive IT industry, then you need the strong expertise knowledge and the accumulated efforts. And pass the AIWMI CCRA-L2 Certification Test Questions exam is not easy. Perhaps through AIWMI CCRA-L2 Certification Test Questions exam you can promote yourself to the IT industry. But it is not necessary to spend a lot of time and effort to learn the expertise. You can choose Omgzlook's AIWMI CCRA-L2 Certification Test Questions exam training materials. This is training product that specifically made for IT exam. With it you can pass the difficult AIWMI CCRA-L2 Certification Test Questions exam effortlessly.

You never know what you can get till you try. It is universally acknowledged that mock examination is of great significance for those who are preparing for the exam since candidates can find deficiencies of their knowledge as well as their shortcomings in the practice test, so that they can enrich their knowledge before the real CCRA-L2 Certification Test Questions exam.

CCRA-L2 PDF DEMO:

QUESTION NO: 1
The most important metric for a bank is the Net Interest Income (NII) which is the difference between____income and____expense.
A. Total; Total
B. Interest; Fee
C. Interest; Interest
D. Interest; Total
Answer: C

QUESTION NO: 2
Scott is a credit analyst with one of the credit rating agencies in India. He was looking in Oil and
Gas Industry companies and has presented brief financials for following 4 entities:
Two credit analysts are discussing the DM-approach to credit risk modeling. They make the following statements:
Analyst A: A portfolio's standard deviation of credit losses can be determined by considering the standard deviation of credit losses of individual exposures in the portfolio and summing them all up.
Analyst B: I do not fully agree with that. Apart from individual standard deviations, one also needs to consider the correlation of the exposure with the rest of the portfolio so as to account for diversification effects. Higher correlations among credit exposures will lead to higher standard deviation of the overall portfolio.
A. Both are correct
B. Only Analyst A is correct
C. Only Analyst B is correct
D. Both are incorrect
Answer: C

QUESTION NO: 3
Which of the following statements concerning having a CEO serve as chairman of the board is most accurate?
Having a CEO also serve as chairman is considered:
A. poor corporate governance practice as having the CEO server as chairman is an inherent conflict when determining management compensation.
B. poor corporate governance practice as having the CEO and chairman serve as separate positions ensures a properly-functioning board.
C. good corporate governance practice as the CEO is the best person to provide the board with information about the company's strategy and operations.
D. cannot be determined
Answer: B

QUESTION NO: 4
Provisioning Coverage Ratio (PCR) is essentially the ratio of provisioning to ______ and indicates the extent of funds a bank has kept aside to cover loan losses.
A. total loan portfolio
B. gross non-performing assets
C. total assets
Answer: B

QUESTION NO: 5
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro power project on river Shiva in Madhya Pradesh (MP). The project is also of relevance from the irrigation perspective due to its location and as per the agreement MCC will have to undertake construction of web of canals, approach road to dam, power house and other ancillary units. MCC is promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges and railway platforms on contract basis for the Government. MCC will have a separate special purpose vehicle (SPV) floated for this venture.
The hydro power project comes under the public private partnership scheme of the Government of
MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant.
The detailed terms of the hydro power project agreement are as follows:1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor. The Government of MP will have to acquire land which will submerge on construction of dam and shall rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government thereafter. Further, SPV shall be tax exempt for a period of five years from DCCO i.e. FY17-FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project is estimated to be commercially operational by April 1, 2016 with two units operational om same day and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the principal.
The expected principal along with capitalized interest is expected to be INR2, 400 Million (i.e.INR2100
Million debt plus INR300 Million capitalized interest). The repayment of the same shall be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From today we are just left with one more year to complete the project in time. However, the flash floods which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point out the loss of lives in the region as you all are well aware of those. Our project has also been badly hit due to the same and we have been assessing the damage over the last one week. After analyzing damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its press release has indicated that they will apply to the higher court on the matter.
Based on the initial projections, do scenario analysis assuming only 75% capacity is utilized in FY17 and FY18 and thereby revenues will be proportionally reduced.
Compute DSCR under such scenario for FY17 and FY18, assuming other things remain constant?
A. FY17: 0.74; FY18: 1.09
B. FY17: 0.85; FY18: 1.26
C. FY17:1.35; FY18: 2.09
D. FY17:0.98; FY18: 1.46
Answer: B

Cisco 300-425 - God wants me to be a person who have strength, rather than a good-looking doll. Under the instruction of our BCS CTFL4 test prep, you are able to finish your task in a very short time and pass the exam without mistakes to obtain the AIWMI certificate. IBM C1000-178 - Most candidates are preparing for IT certification exam while they working, which is a painstaking, laborious process. So many our customers have benefited form our IBM C1000-065 preparation quiz, so will you! Have you ever used Omgzlook AIWMI Salesforce B2C-Commerce-Developer dumps? The braindump is latest updated certification training material, which includes all questions in the real exam that can 100% guarantee to pass your exam.