1Z0-520 Latest Exam Vce - 1Z0-520 Latest Cram Materials & Oracle EBS R12.1 Purchasing Essentials - Omgzlook

If you want to spend the least time to achieve your goals, 1Z0-520 Latest Exam Vce learning materials are definitely your best choice. You can really try it we will never let you down! Under the leadership of a professional team, we have created the most efficient learning 1Z0-520 Latest Exam Vce training guide for our users. As a IT worker sometime you may know you will take advantage of new technology more quickly by farming out computer operations, we prefer to strengthen own strong points. Our 1Z0-520 Latest Exam Vce test braindump materials is popular based on that too. Our highly efficient operating system for learning materials has won the praise of many customers.

E Business Suite 1Z0-520 As you know, life is like the sea.

If you are willing, our 1Z0-520 - Oracle EBS R12.1 Purchasing Essentials Latest Exam Vce training PDF can give you a good beginning. Our experts made significant contribution to their excellence of the Pdf 1Z0-520 Files study materials. So we can say bluntly that our Pdf 1Z0-520 Files simulating exam is the best.

We provide our customers with the most reliable learning materials about 1Z0-520 Latest Exam Vce certification exam and the guarantee of pass. We assist you to prepare the key knowledge points of 1Z0-520 Latest Exam Vce actual test and obtain the up-to-dated exam answers. All 1Z0-520 Latest Exam Vce test questions offered by us are tested and selected by our senior experts in IT filed, which only need little time to focus on the practice and the preparation.

Now, quickly download Oracle 1Z0-520 Latest Exam Vce free demo for try.

Being anxious for the 1Z0-520 Latest Exam Vce exam ahead of you? Have a look of our 1Z0-520 Latest Exam Vce training engine please. Presiding over the line of our practice materials over ten years, our experts are proficient as elites who made our 1Z0-520 Latest Exam Vce learning questions, and it is their job to officiate the routines of offering help for you. All points are predominantly related with the exam ahead of you. You will find the exam is a piece of cake with the help of our 1Z0-520 Latest Exam Vce study materials.

You just need 20-30 hours for preparation and feel confident to face the 1Z0-520 Latest Exam Vce actual test. 1Z0-520 Latest Exam Vce questions & answers cover all the key points of the real test.

1Z0-520 PDF DEMO:

QUESTION NO: 1
ABC Company uses serial numbers for the following transactions:
1. Purchase order receipt
2. Miscellaneous receipt
3. Account alias receipt
The company wants to reuse the same serial numbers for work order completion transactions.
Which setup would allow it to reuse the same serial numbers?
A. INV: Restrict Receipt of Serials: No
B. INV: Validate Returned Lot: Yes and INV: Validate Returned Serial: No
C. INV: Validate Returned Serial: No
D. INV: Restrict Receipt of Serials: Yes and INV: Validate Returned Serial: Yes
E. INV: Restrict Receipt of Serials: Yes
F. INV: Restrict Receipt of Serials: Yes and INV: Validate Returned Serial: No
G. INV: Validate Returned Serial: Yes
Answer: A

QUESTION NO: 2
Select the true statement about Material Status Control.
A. The profile option "INV: Allow Expense to Asset Transfer" must be set to Yes at the application level to enforce Material Status Control.
B. The profile option "INV: Material Status Support" must be set to Yes at the site level to enforce
Material Status Control.
C. The profile option "INV: Transaction Reasons Security" must be set to Yes at the site level to enforce Material Status Control.
D. The profile option "INV: Default Item Status" must be set to Active at the site level to enforce
Material Status Control.
Answer: B

QUESTION NO: 3
BC Inc. added a new Operating Unit to its existing Multi-Org Access-enabled responsibility.
When users logged in using their existing responsibility, they could not see the new Operating Unit in the list of values.
What could be the cause?
A. The Set MO: Operating Unit profile was not defined.
B. The Set Multi-Org Preferences profile was not defined.
C. The Set MO: Default Operating Unit profile was not defined.
D. The Set MO: Security profile was not defined for the responsibility.
E. Security List Maintenance was not run.
Answer: E

QUESTION NO: 4
View the Exhibit.
Your client was creating an express receipt. While saving the receipt, it failed. Identify the most logical reason for the failure.
A. A manual action was performed in one of the lines before clicking the Express button.
B. Instead of a purchase order number, a supplier name was specified in the Find Expected Receipts window.
C. Location is not available for Expense Destination Type and the Destination Type is Receiving.
D. Location is not available for Expense Destination Type and the Destination Type is Final
Destination.
E. The Early/late Receipt Date Tolerance is exceeded and the Exception Control is Warning.
Answer: D

QUESTION NO: 5
Identify the correct sequence of steps in the Procure to Pay period dose process.
A. Prepare for period dose. > Run Validation/ Review and resolve holds. > Create accounting. >
Transfer and review. > Close the period in AP. > Post journal entries in GL > Reconcile AP activity for the period. > Close the PO period.
B. Prepare for period dose. > Run Validation/ Review and resolve holds. > Create accounting. >
Transfer and review. > Close the period in AP. > Reconcile AP activity for the period. > Post journal entries in GL > Close the PO period.
C. Prepare for period close. > Run Validation/ Review and resolve holds. > Create accounting. >
Transfer and review. > Close the period in AP. > Reconcile AP activity for the period. > Close the PO period. > Post journal entries in GL
D. Prepare for period dose. > Run Validation/ Review and resolve holds. > Transfer and review. >
Close the period in AP. > Create accounting. > Post journal entries in GL. > Reconcile AP activity for the period. > Close the PO period.
E. Prepare for period dose. > Run Validation/ Review and resolve holds. > Create accounting. >
Transfer and review. > Close the period in PO. > Post journal entries in GL > Reconcile PO activity for the period. > Close the AP period.
Answer: A

And so many of our loyal customers have achieved their dreams with the help of our SAP C_ARSOR_2404 exam questions. Immediately after you have made a purchase for our Microsoft MB-240 practice dumps, you can download our Microsoft MB-240 study materials to make preparations. If you have bought the Huawei H14-331_V1.0 exam questions before, then you will know that we have free demos for you to download before your purchase. EMC D-MN-OE-23 - You must use it before the deadline day. By concluding quintessential points into Microsoft AZ-801 actual exam, you can pass the exam with the least time while huge progress.