CCRA-L2 Pdf Braindumps - Aiwmi Certified Credit Research Analyst Level 2 Reliable Test Tips - Omgzlook

CCRA-L2 Pdf Braindumps training materials have now provided thousands of online test papers for the majority of test takers to perform simulation exercises, helped tens of thousands of candidates pass the CCRA-L2 Pdf Braindumps exam, and got their own dream industry certificates CCRA-L2 Pdf Braindumps exam questions have an extensive coverage of test subjects and have a large volume of test questions, and an online update program. CCRA-L2 Pdf Braindumps training materials are not only the passbooks for students passing all kinds of professional examinations, but also the professional tools for students to review examinations. In the past few years, CCRA-L2 Pdf Braindumps exam torrent hasreceived the trust of a large number of students and also helped a large number of students pass the exam smoothly. Close to 100% passing rate is the best gift that our customers give us. We also hope our CCRA-L2 Pdf Braindumps exam materials can help more ambitious people pass CCRA-L2 Pdf Braindumps exam. People often complain that they are wasting their time on study and work.

AIWMI CCRA CCRA-L2 The secret of success is constancy to purpose.

AIWMI CCRA CCRA-L2 Pdf Braindumps - Certified Credit Research Analyst Level 2 You will get more opportunities than others, and your dreams may really come true in the near future. Then you can pass the actual test quickly and get certification easily. The CCRA-L2 Valid Exam Test real questions are written and approved by our It experts, and tested by our senior professionals with many years' experience.

The CCRA-L2 Pdf Braindumps study braindumps are compiled by our frofessional experts who have been in this career fo r over ten years. Carefully written and constantly updated content of our CCRA-L2 Pdf Braindumps exam questions can make you keep up with the changing direction of the exam, without aimlessly learning and wasting energy. In addition, there are many other advantages of our CCRA-L2 Pdf Braindumps learning guide.

You will never worry about the AIWMI CCRA-L2 Pdf Braindumps exam.

To cope with the fast growing market, we will always keep advancing and offer our clients the most refined technical expertise and excellent services about our CCRA-L2 Pdf Braindumps exam questions. In the meantime, all your legal rights will be guaranteed after buying our CCRA-L2 Pdf Braindumps study materials. For many years, we have always put our customers in top priority. Not only we offer the best CCRA-L2 Pdf Braindumps training prep, but also our sincere and considerate attitude is praised by numerous of our customers.

So we never stop the pace of offering the best services and CCRA-L2 Pdf Braindumps practice materials for you. Tens of thousands of candidates have fostered learning abilities by using our CCRA-L2 Pdf Braindumps Learning materials you can be one of them definitely.

CCRA-L2 PDF DEMO:

QUESTION NO: 1
Mark Construction Company (MCC) has bagged a contract for construction of a large dam and hydro power project on river Shiva in Madhya Pradesh (MP). The project is also of relevance from the irrigation perspective due to its location and as per the agreement MCC will have to undertake construction of web of canals, approach road to dam, power house and other ancillary units. MCC is promoted by Mr. Thomas Mark, who is a MP from the ruling party which recently formed government in MP. Historically, MCC has been engaged into construction of rural roads, small bridges and railway platforms on contract basis for the Government. MCC will have a separate special purpose vehicle (SPV) floated for this venture.
The hydro power project comes under the public private partnership scheme of the Government of
MP, where in the private partner builds owns operates and transfers (BOOT) the hydro power plant.
The detailed terms of the hydro power project agreement are as follows:1. The construction of the dam, canals and hydro power plant shall be undertaken by the contractor. The Government of MP will have to acquire land which will submerge on construction of dam and shall rehabilitate the owners of land.
2. MCC shall have right to operate the hydro power project from date of commencement of commercial operations (DCCO) for a period of 20 years and shall transfer the project to Government thereafter. Further, SPV shall be tax exempt for a period of five years from DCCO i.e. FY17-FY21.
3. The power project is of 600 megawatts (MW) shall comprise 4 units of 150 MW each. The estimated cost of project is about INR3, 500 Million to be spent over a period of 4 year(s) the project is estimated to be commercially operational by April 1, 2016 with two units operational om same day and one unit each will be operational on April 1, 2017 and April 1, 2018.
4. Means of finance:
Means of Finance INR Million
Government Aid (To be classified as Equity) 500Equity 900 Debt 2100
5. Amount if expenditure estimated in various years is as follows:
Debt shall bear a fixed rate of interest of 10% and all interest till DCCO shall be added to the principal.
The expected principal along with capitalized interest is expected to be INR2, 400 Million (i.e.INR2100
Million debt plus INR300 Million capitalized interest). The repayment of the same shall be in 12 equated annual installments starting from FY17.
Brief projections for the period of FY17 to FY21 are given below:
Developments as on March 31, 2015
The project manager for the SPV made following comments at a press conferee on March 31, 2015:
As you all are aware, we were running bang on schedule till we last met on December 21, 2014. From today we are just left with one more year to complete the project in time. However, the flash floods which struck our dam site on this March 15, 2015 have created havoc in the region. I shall not point out the loss of lives in the region as you all are well aware of those. Our project has also been badly hit due to the same and we have been assessing the damage over the last one week. After analyzing damage, we have made changes in project schedule. Now we will be making only one unit of 150
MW operational on April 1, 2016 and 1 unit each will be added in each of subsequent year(s).
Development as on September 30, 2015
Post the flash floods, lot of environmentalists started raising issues of changes in environment due to construction of large number of dams. A few Public Interest Litigations (PILs) have been filed in various courts.
Honorable High Court of MP on September 27, 2015, banned construction of any dams in the region and banned permissions for new dams till next hearing scheduled on November 30, 2015. MCC in its press release has indicated that they will apply to the higher court on the matter.
Based on the initial projections, do scenario analysis assuming only 75% capacity is utilized in FY17 and FY18 and thereby revenues will be proportionally reduced.
Compute DSCR under such scenario for FY17 and FY18, assuming other things remain constant?
A. FY17: 0.74; FY18: 1.09
B. FY17: 0.85; FY18: 1.26
C. FY17:1.35; FY18: 2.09
D. FY17:0.98; FY18: 1.46
Answer: B

QUESTION NO: 2
The most important metric for a bank is the Net Interest Income (NII) which is the difference between____income and____expense.
A. Total; Total
B. Interest; Fee
C. Interest; Interest
D. Interest; Total
Answer: C

QUESTION NO: 3
Scott is a credit analyst with one of the credit rating agencies in India. He was looking in Oil and
Gas Industry companies and has presented brief financials for following 4 entities:
Two credit analysts are discussing the DM-approach to credit risk modeling. They make the following statements:
Analyst A: A portfolio's standard deviation of credit losses can be determined by considering the standard deviation of credit losses of individual exposures in the portfolio and summing them all up.
Analyst B: I do not fully agree with that. Apart from individual standard deviations, one also needs to consider the correlation of the exposure with the rest of the portfolio so as to account for diversification effects. Higher correlations among credit exposures will lead to higher standard deviation of the overall portfolio.
A. Both are correct
B. Only Analyst A is correct
C. Only Analyst B is correct
D. Both are incorrect
Answer: C

QUESTION NO: 4
Which of the following statements concerning having a CEO serve as chairman of the board is most accurate?
Having a CEO also serve as chairman is considered:
A. poor corporate governance practice as having the CEO server as chairman is an inherent conflict when determining management compensation.
B. poor corporate governance practice as having the CEO and chairman serve as separate positions ensures a properly-functioning board.
C. good corporate governance practice as the CEO is the best person to provide the board with information about the company's strategy and operations.
D. cannot be determined
Answer: B

QUESTION NO: 5
Provisioning Coverage Ratio (PCR) is essentially the ratio of provisioning to ______ and indicates the extent of funds a bank has kept aside to cover loan losses.
A. total loan portfolio
B. gross non-performing assets
C. total assets
Answer: B

Even the SAP C-LIXEA-2404 test syllabus is changing every year; our experts still have the ability to master the tendency of the important knowledge as they have been doing research in this career for years. Our EMC D-VPX-DY-A-24 study materials provide a promising help for your EMC D-VPX-DY-A-24 exam preparation whether newbie or experienced exam candidates are eager to have them. IBM C1000-101-KR - So do not hesitate and hurry to buy our study materials. By analyzing the syllabus and new trend, our Microsoft AZ-801 practice engine is totally in line with this exam for your reference. CheckPoint 156-521 - We must realize our own values and make progress.