1Z0-062 Mock Exams - Oracle Database 12C: Installation And Administration Valid Test Duration - Omgzlook

You only take 20 to 30 hours to practice our 1z0-062 Mock Exams guide materials and then you can take the exam. If you use our study materials, you can get the 1z0-062 Mock Exams certification by spending very little time and energy reviewing and preparing. A good 1z0-062 Mock Exams certification must be supported by a good 1z0-062 Mock Exams exam practice, which will greatly improve your learning ability and effectiveness. And there is no exaggeration that our pass rate for our 1z0-062 Mock Exams study guide is 98% to 100% which is proved and tested by our loyal customers. As you may see the data on the website, our sales volumes of our 1z0-062 Mock Exams exam questions are the highest in the market. If you want to pass the exam smoothly buying our Oracle Database 12c: Installation and Administration guide dump is your ideal choice.

Oracle Database 1z0-062 Just buy it and you will love it!

Oracle Database 1z0-062 Mock Exams - Oracle Database 12c: Installation and Administration Your current achievements cannot represent your future success. If you are satisfied with our 1z0-062 Test Engine training guide, come to choose and purchase. If you buy the Software or the APP online version of our 1z0-062 Test Engine study materials, you will find that the timer can aid you control the time.

We have free demos on the website for our customers to download if you still doubt our products, and you can check whether it is the right one for you before purchase as well. Our 1z0-062 Mock Exams exam materials are famous among candidates. Once they need to prepare an exam, our 1z0-062 Mock Exams study materials are their first choice.

Our Oracle 1z0-062 Mock Exams practice quiz is unique in the market.

With the improvement of people’s living standards, there are more and more highly educated people. To defeat other people in the more and more fierce competition, one must demonstrate his extraordinary strength. Today, getting 1z0-062 Mock Exams certification has become a trend, and 1z0-062 Mock Exams exam dump is the best weapon to help you pass certification. We all know that obtaining the 1z0-062 Mock Exams certification is very difficult, and students who want to pass the exam often have to spend a lot of time and energy. After years of hard work, the experts finally developed a set of perfect learning materials 1z0-062 Mock Exams practice materials that would allow the students to pass the exam easily. With our study materials, you only need 20-30 hours of study to successfully pass the exam and reach the peak of your career. What are you waiting for? Come and buy it now.

And our website has already became a famous brand in the market because of our reliable 1z0-062 Mock Exams exam questions. Different from all other bad quality practice materials that cheat you into spending much money on them, our 1z0-062 Mock Exams exam materials are the accumulation of professional knowledge worthy practicing and remembering.

1z0-062 PDF DEMO:

QUESTION NO: 1
Which two statements are true about the (PMON) background process in Oracle Database
12c? (Choose two.)
A. It frees unused temporary segments.
B. It kills sessions that exceed idle time.
C. It frees resources held by abnormally terminated processes.
D. It registers database services with all local and remote listeners known to the database instance.
E. It records checkpoint information in the control file.
Answer: C,D
Explanation
References: https://docs.oracle.com/database/122/CNCPT/process-architecture.htm#CNCPT9840

QUESTION NO: 2
Your database is open and the listener LISTENER is up. You issue the command:
LSNRCTL> RELOAD
What is the effect of RELOAD on sessions that were originally established by LISTENER?
A. Only sessions based on static listener registrations are disconnected.
B. The sessions are not affected and continue to function normally.
C. All the sessions are terminated and active transactions are rolled back.
D. Existing connections are not disconnected; however, they cannot perform any operations until the listener completes the re-registration of the database instance and service handlers.
Answer: B

QUESTION NO: 3
Which four statements are true about the components of the Oracle Scheduler? (Choose four.)
A. A job may get started automatically when a window opens.
B. A job is specified as part of a program specification.
C. A program can be used in the definition of multiple jobs.
D. A program and schedule can be specified as part of a job definition.
E. A scheduler job can point to a chain instead of pointing to a single program object.
F. A program and job can be specified as part of a schedule definition.
G. A schedule can be specified to a single job only.
Answer: A,C,D,E
Explanation
References: https://docs.oracle.com/cd/B19306_01/server.102/b14231/schedover.htm

QUESTION NO: 4
Which statement is true about Oracle Net Listener?
A. A single listener can service only one database instance and multiple remote client connections.
B. It acts as the listening endpoint for the Oracle database instance for all local and non-local user connections.
C. Service registration with the listener is performed by the process monitor (PMON) process of each database instance.
D. The listener.ora configuration file must be located in the ORACLE_HOME/network/admin directly.
E. The listener.ora configuration file must be configured with one or more listening protocol addresses to allow remote users to connect to a database instance.
Answer: C
Explanation
https://docs.oracle.com/database/121/CNCPT/process.htm

QUESTION NO: 5
Which two statements are true concerning the Resource Manager plans for individual pluggable databases (PDB plans) in a multitenant container database (CDB)? (Choose two.)
A. If a PDB plan is enabled for a pluggable database, then resources are allocated to consumer groups based on the shares provided to the PDB in the CDB plan and the shares provided to the consumer groups in the PDB plan.
B. If no PDB plan is enabled for a pluggable database, then all sessions for that PDB are treated to an equal degree of the resource share of that PDB.
C. If a PDB plan is enabled for a pluggable database, then resources are allocated to consumer groups across all PDBs in the CDB.
D. In a PDB plan, subplans may be used with up to eight consumer groups.
E. If no PDB plan is enabled for a pluggable database, then the PDB share in the CDB plan is dynamically calculated.
Answer: A,B
Explanation
A: Setting a PDB resource plan is optional. If not specified, all sessions within the PDB are treated equally.
* In a non-CDB database, workloads within a database are managed with resource plans.
In a PDB, workloads are also managed with resource plans, also called PDB resource plans.
The functionality is similar except for the following differences:
/ Non-CDB Database
Multi-level resource plans
Up to 32 consumer groups
Subplans
/ PDB Database
Single-level resource plans only
Up to 8 consumer groups
(not B) No subplans

Are you still feeling distressed for expensive learning materials? Are you still struggling with complicated and difficult explanations in textbooks? Do you still hesitate in numerous tutorial materials? HP HP2-I71 study guide can help you to solve all these questions. ITIL ITIL-4-Foundation - For more textual content about practicing exam questions, you can download our products with reasonable prices and get your practice begin within 5 minutes. Microsoft AZ-700 - You can directly select our products. ISACA COBIT-Design-and-Implementation - And you can free donwload the demos to have a look. So every year a large number of people take Fortinet FCP_FWF_AD-7.4 tests to prove their abilities.