PSM-II Reliable Real Test Question & Test PSM-II Dumps Pdf & PSM-II Latest Test Cram Review - Omgzlook

We are concentrating on the reform on the PSM-II Reliable Real Test Question exam material that our candidates try to get aid with. We own the profession experts on compiling the PSM-II Reliable Real Test Question practice questions and customer service on giving guide on questions from our clients. Our PSM-II Reliable Real Test Question preparation materials contain three versions: the PDF, the Software and the APP online. Our PSM-II Reliable Real Test Question exam materials have plenty of advantages. For example, in order to meet the needs of different groups of people, we provide customers with three different versions of PSM-II Reliable Real Test Question actual exam, which contain the same questions and answers. And our software of the PSM-II Reliable Real Test Question training material also allows different users to study at the same time.

Professional Scrum Master PSM-II Repeated attempts will sharpen your minds.

PSM-II - Professional Scrum Master level II (PSM II) Reliable Real Test Question exam questions promise that if you fail to pass the exam successfully after purchasing our product, we are willing to provide you with a 100% full refund. It is time for you to plan your life carefully. After all, you have to make money by yourself.

We will send our PSM-II Reliable Real Test Question exam question in 5-10 minutes after their payment. Because the most clients may be busy in their jobs or other significant things, the time they can spare to learn our PSM-II Reliable Real Test Question learning guide is limited and little. But if the clients buy our PSM-II Reliable Real Test Question training quiz they can immediately use our product and save their time.

Scrum PSM-II Reliable Real Test Question - Please make a decision quickly.

Today, in an era of fierce competition, how can we occupy a place in a market where talent is saturated? The answer is a certificate. What the certificate main? All kinds of the test PSM-II Reliable Real Test Question certification, prove you through all kinds of qualification certificate, it is not hard to find, more and more people are willing to invest time and effort on the PSM-II Reliable Real Test Question exam guide, because get the test PSM-II Reliable Real Test Question certification is not an easy thing, so, a lot of people are looking for an efficient learning method. And here, fortunately, you have found the PSM-II Reliable Real Test Question exam braindumps, a learning platform that can bring you unexpected experiences.

The product of Omgzlook not only can 100% guarantee you to pass the exam, but also can provide you a free one-year update service. If you choose Omgzlook, success is not far away for you.

PSM-II PDF DEMO:

QUESTION NO: 1
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 2
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C

QUESTION NO: 3
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 4
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

QUESTION NO: 5
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C

The software version is one of the three versions of our Fortinet NSE6_WCS-7.0 actual exam, which is designed by the experts from our company. They would choose this difficult Scrum certification Cisco 350-601 exam to get certification and gain recognition in IT area. We have printable PDF format that you can study our Cisco 300-425 training engine anywhere and anytime since it is printable. You can free download part of Omgzlook's exercises and answers about Scrum certification Network Appliance NS0-604 exam as a try, then you will be more confident to choose our Omgzlook's products to prepare your Scrum certification Network Appliance NS0-604 exam. Huawei H20-421_V1.0 - You can choose your most desirable way to practice on the daily basis.