PSM-II Reliable Exam Preparation - Scrum Original PSM-II Questions - Professional Scrum Master Level Ii PSM-II - Omgzlook

You can learn our PSM-II Reliable Exam Preparation test questions at any time and place. The APP online version is used and designed based on the web browser. Any equipment can be used if only they boost the browser. By virtue of our PSM-II Reliable Exam Preparation practice materials, many customers get comfortable experiences of Whole Package of Services and of course passing the PSM-II Reliable Exam Preparation study guide successfully. Our company conducts our business very well rather than unprincipled company which just cuts and pastes content from others and sell them to exam candidates.All candidate are desperately eager for useful PSM-II Reliable Exam Preparation actual exam, our products help you and we are having an acute shortage of efficient PSM-II Reliable Exam Preparation exam questions. So our experts highlights the new type of questions and add updates into the PSM-II Reliable Exam Preparation practice materials, and look for shifts closely when them take place.

Professional Scrum Master PSM-II You can totally rely on us!

PSM-II - Professional Scrum Master level II (PSM II) Reliable Exam Preparation study engine is very attentive to provide a demo for all customers who concerned about our products, whose purpose is to allow customers to understand our product content before purchase. The download and install set no limits for the amount of the computers and the persons who use Valid Study PSM-II Questions Pdf test prep. So we provide the best service for you as you can choose the most suitable learning methods to master the Valid Study PSM-II Questions Pdf exam torrent.

If you have any questions after you buy our PSM-II Reliable Exam Preparation study guide, you can always get thoughtful support and help by email or online inquiry. If you neeed any support, and we are aways here to help you. Our considerate service is not only reflected in the purchase process, but also reflected in the considerate after-sales assistance on our PSM-II Reliable Exam Preparation exam questions.

Scrum PSM-II Reliable Exam Preparation - You must be very surprised.

Our PSM-II Reliable Exam Preparation exam quiz is unlike other exam materials that are available on the market, our PSM-II Reliable Exam Preparation study dumps specially proposed different versions to allow you to learn not only on paper, but also to use mobile phones to learn. This greatly improves the students' availability of fragmented time. So you can achieve your PSM-II Reliable Exam Preparation certification easily without disrupting your daily routine. And we will give you 100% success guaranteed on the PSM-II Reliable Exam Preparation training guide.

In short, you will find the convenience and practicality of our PSM-II Reliable Exam Preparation quiz guide in the process of learning. We will also continue to innovate and improve functions to provide you with better services.

PSM-II PDF DEMO:

QUESTION NO: 1
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

QUESTION NO: 2
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 3
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.

QUESTION NO: 4
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 5
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
A. Ask the Development Team member to share the issue with the team as soon as possible.
B. Notify the test team.
C. Add a Product Backlog item to address the security issue.
D. Wait until the Sprint Retrospective to add security to the definition of "Done".
Answer: A
Explanation:
It is best to coach the Development Team members to collaborate on issues regardless of severity.
They may consult the Scrum Master of Product Owner if needed.

We are convinced that our ISQI CPSA-FL exam questions can help you gain the desired social status and thus embrace success. CheckPoint 156-315.81 - Everybody knows that in every area, timing counts importantly. Our SAP C_DBADM_2404 exam questions are your best choice. Our IBM C1000-178 exam questions have been widely acclaimed among our customers, and the good reputation in industry prove that choosing our study materials would be the best way for you, and help you gain the IBM C1000-178 certification successfully. Our Fortinet NSE7_LED-7.0 learning questions engage our working staff in understanding customers’ diverse and evolving expectations and incorporate that understanding into our strategies, thus you can 100% trust our Fortinet NSE7_LED-7.0 exam engine.

Updated: May 27, 2022