PSM-II Exam Questions Answers - Scrum Exam PSM-II Success - Professional Scrum Master Level Ii PSM-II - Omgzlook

If you fail in the PSM-II Exam Questions Answers actual test, we will give you full refund. If you have other exam to be taken, we can free replace it for you. PSM-II Exam Questions Answers latest cram material covers all the sections of the actual exam. We have hired professional staff to maintain PSM-II Exam Questions Answers practice engine and our team of experts also constantly updates and renew the question bank according to changes in the syllabus. With PSM-II Exam Questions Answers learning materials, you can study at ease, and we will help you solve all the problems that you may encounter in the learning process. Our experts constantly keep the pace of the current exam requirement for PSM-II Exam Questions Answers actual test to ensure the accuracy of our questions.

Professional Scrum Master PSM-II Then you can learn and practice it.

Professional Scrum Master PSM-II Exam Questions Answers - Professional Scrum Master level II (PSM II) With Omgzlook real questions and answers, when you take the exam, you can handle it with ease and get high marks. As the quick development of the world economy and intense competition in the international, the world labor market presents many new trends: company’s demand for the excellent people is growing. As is known to us, the Free PSM-II Download certification is one mainly mark of the excellent.

Do you wonder why so many peers can successfully pass PSM-II Exam Questions Answers exam? Are also you eager to obtain PSM-II Exam Questions Answers exam certification? Now I tell you that the key that they successfully pass the exam is owing to using our PSM-II Exam Questions Answers exam software provided by our Omgzlook. Our PSM-II Exam Questions Answers exam software offers comprehensive and diverse questions, professional answer analysis and one-year free update service after successful payment; with the help of our PSM-II Exam Questions Answers exam software, you can improve your study ability to obtain PSM-II Exam Questions Answers exam certification.

Scrum PSM-II Exam Questions Answers - Omgzlook is worthy your trust.

We are willing to provide all people with the demo of our PSM-II Exam Questions Answers study tool for free. If you have any doubt about our products that will bring a lot of benefits for you. The trial demo of our PSM-II Exam Questions Answers question torrent must be a good choice for you. By the trial demo provided by our company, you will have the opportunity to closely contact with our PSM-II Exam Questions Answers exam torrent, and it will be possible for you to have a view of our products. More importantly, we provide all people with the trial demo for free before you buy our PSM-II Exam Questions Answers exam torrent and it means that you have the chance to download from our web page for free; you do not need to spend any money.

PSM-II Exam Questions Answers exam seems just a small exam, but to get the PSM-II Exam Questions Answers certification exam is to be reckoned in your career. Such an international certification is recognition of your IT skills.

PSM-II PDF DEMO:

QUESTION NO: 1
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C

QUESTION NO: 2
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C

QUESTION NO: 3
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 4
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 5
Who should be present to review and adjust the selected Sprint work if the Development Team determines that it will not be able to finish the complete forecast?
A. The Development Team and Project Manager.
B. The Scrum Master, the Business Analyst and the Development Team.
C. The stakeholders and Scrum Master.
D. The Product Owner and the Development Team.
Answer: D

APM APM-PFQ - Because many users are first taking part in the exams, so for the exam and test time distribution of the above lack certain experience, and thus prone to the confusion in the examination place, time to grasp, eventually led to not finish the exam totally. We provide the SAP C_ARCIG_2404 test engine with self-assessment features for enhanced progress. To improve our products’ quality we employ first-tier experts and professional staff and to ensure that all the clients can pass the test we devote a lot of efforts to compile the HP HP2-I65 learning guide. If you fail exam with our exam questions, you just need to send your ISM INTE failure score scanned to our email address, we will full refund to you soon without any other doubt. SAP C-THR82-2405 - It doesn’t matter.