Therefore, purchasing the 70-294 Test Certification Cost guide torrent is the best and wisest choice for you to prepare your test. If you buy our 70-294 Test Certification Cost questions torrent, the day of regretting will not come anymore. It is very economical that you just spend 20 or 30 hours then you have the 70-294 Test Certification Cost certificate in your hand, which is typically beneficial for your career in the future. Our expert team will check the update 70-294 Test Certification Cost learning prep and will send the update version automatically to the clients. So the clients can enjoy the convenience of our wonderful service and the benefits brought by our superior 70-294 Test Certification Cost guide materials. You will not need to struggle with the exam.

MCSE2003 Messaging 70-294 More detailed information is under below.

And at the same time, you don't have to pay much time on the preparation for our 70-294 - Planning, Implementing, and Maintaining a Microsoft Windows Server 2003 AD Infrastructure Test Certification Cost learning guide is high-efficient. What's more, during the whole year after purchasing, you will get the latest version of our 70-294 Reliable Test Online study materials for free. You can see that there are only benefits for you to buy our 70-294 Reliable Test Online learning guide, so why not just have a try right now?

We are willing to recommend you to try the 70-294 Test Certification Cost learning guide from our company. Our products are high quality and efficiency test tools for all people with three versions which satisfy all your needs. If you buy our 70-294 Test Certification Cost preparation questions, you can use our 70-294 Test Certification Cost practice engine for study in anytime and anywhere.

Microsoft 70-294 Test Certification Cost - Why not have a try?

As is known to us, getting the newest information is very important for all people to pass the exam and get the certification in the shortest time. In order to help all customers gain the newest information about the 70-294 Test Certification Cost exam, the experts and professors from our company designed the best Planning, Implementing, and Maintaining a Microsoft Windows Server 2003 AD Infrastructure test guide. The experts will update the system every day. If there is new information about the exam, you will receive an email about the newest information about the 70-294 Test Certification Cost learning dumps. We can promise that you will never miss the important information about the exam.

With our 70-294 Test Certification Cost exam questions, you will easily get the favor of executives and successfully enter the gates of famous companies. You will have higher wages and a better development platform.

70-294 PDF DEMO:

QUESTION NO: 1
Your company has a main office and a single branch office. The two offices are connected through a
WAN link. You have Active Directory directory service site objects for each office. Domain controllers are associated with the appropriate site objects.
Users in the main office are currently authenticated by domain controllers in the branch office.
You need to ensure that users in the main office are authenticated by the domain controllers in the main office.
What should you do?
A. Clear the Bridge all site links option.
B. Configure a preferred bridgehead server for the site for the main office.
C. Associate the subnets for the main office with the site for the main office.
D. Associate the subnets for the branch office with the site for the branch office.
Answer: C

QUESTION NO: 2
Your company has a single Active Directory directory service domain. The company has five Active
Directory sites on the West coast and five Active Directory sites on the East coast. The West coast sites and the East coast sites are in two separate hub-and-spoke configurations that are separated by a firewall.
All Active Directory replication between the West coast and East coast occurs between a single West coast domain controller named WestDC1 and a single East coast domain controller named EastDC1.
You need to ensure that if WestDC1 fails, other West coast domain controllers continue to replicate with each other, but not with East coast domain controllers.
What should you do?
A. Create site links between the West coast hub site and the West coast spoke sites.
B. Create a site link bridge between the West coast hub site and the East coast hub site.
C. Clear the Bridge all site links option and create a site link bridge for all the East coast sites.
D. Clear the Bridge all site links option and create a site link bridge for all the West coast sites.
Answer: D

QUESTION NO: 3
You have a single Active Directory directory service domain. There is a branch office that connects to the main office through a low-bandwidth WAN link.
The first domain controller is named DC1 and is located in the main office. The branch office has a single server named Server1. Server1 runs Windows Server 2003.
You are preparing to install Active Directory on Server1. You back up the system state of DC1, and you send the backup to the administrator at the branch office.
You need to make Server1 an additional domain controller in your domain, while minimizing the bandwidth usage between the two offices.
What should you do?
A. Restore the system state data from DC1 to an alternate location on Server1. Run the dcpromo command with the /adv parameter, and select the From these restored backup files option.
B. Restore the system state data from DC1 to the original location on Server1. Run the dcpromo command with the /adv parameter, and select the From these restored backup files option.
C. Create a new Active Directory site. Create an unattended installation file with the
CriticalReplicationOnly parameter. Run the dcpromo command with the /answer parameter.
D. Create a new Active Directory site. Create an unattended installation file with the SiteName parameter to place Server1 into the new site. Run the dcpromo command with the /answer parameter.
Answer: A

QUESTION NO: 4
You have a single Active Directory directory service domain. Your company has a main office and multiple branch offices. Each office has an Active Directory site. The company s network is not fully routed.
You need to ensure complete replication between the Active Directory sites.
What should you do?
A. Configure site links, and disable site link bridging.
B. Configure site links to use the SMTP transport, and enable site link bridging.
C. Configure a preferred bridgehead server for each branch office site.
D. Configure a preferred bridgehead server for the main office site.
Answer: A

QUESTION NO: 5
Your company has a single Active Directory directory service forest with a forest root domain and a child domain. The company has a main office and several branch offices. You are planning to remove the child domain.
All of the domain controllers in the forest root domain are located in the main office, and all FSMO roles are on separate domain controllers. The last domain controller in the child domain is named DC1 and is located in a branch office.
You attempt to remove Active Directory from DC1, but you receive an error message stating that the operation could not be completed.
You need to remove Active Directory from DC1.
What should you do?
A. Restore connectivity to the domain controller that holds the Domain Naming Master role.
B. Restore connectivity to the domain controller that holds the Schema Master role.
C. Restore connectivity to the domain controller that holds the Infrastructure Master role.
D. Restore connectivity to the domain controller that holds the PDC Emulator role.
Answer: A

Although the three major versions of our VMware 1V0-41.20 exam dumps provide a demo of the same content for all customers, they will meet different unique requirements from a variety of users based on specific functionality. NAHP NRCMA - For most users, access to the relevant qualifying examinations may be the first, so many of the course content related to qualifying examinations are complex and arcane. AACE International CCP - The Internet is increasingly becoming a platform for us to work and learn, while many products are unreasonable in web design, and too much information is not properly classified. Therefore, getting the test SAP P-BTPA-2408 certification is of vital importance to our future employment. Pegasystems PEGACPBA88V1 - You must make a decision as soon as possible!