PSM-II Test Blueprint & Scrum PSM-II Free Study Material - Professional Scrum Master Level Ii PSM-II - Omgzlook

Because it will make you pass the exam easily, since then rise higher and higher on your career path. Omgzlook is website that can help a lot of IT people realize their dreams. If you have a IT dream, then quickly click the click of Omgzlook. At present, our PSM-II Test Blueprintstudy materials can give you a ray of hope. You can get the PSM-II Test Blueprint certification easily with our PSM-II Test Blueprint learning questions and have a better future. Moreover, we can give you a year of free updates until you pass the exam.

Professional Scrum Master PSM-II So try to trust us.

Professional Scrum Master PSM-II Test Blueprint - Professional Scrum Master level II (PSM II) Only if you choose to use exam dumps Omgzlook provides, you can absolutely pass your exam successfully. Our windows software and online test engine of the PSM-II Reliable Exam Camp Materials exam questions are suitable for all age groups. At the same time, our operation system is durable and powerful.

Many times getting a right method is important and more efficient than spending too much time and money in vain. Our Omgzlook team devote themselves to studying the best methods to help you pass PSM-II Test Blueprint exam certification. From the time when you decide whether to purchase our PSM-II Test Blueprint exam software or not, we have provided you with comprehensive guarantees, including free demo download before buying, payment guarantee in purchase process, one-year free update service after you purchased PSM-II Test Blueprint exam software, and full refund guarantee of dump cost if you fail PSM-II Test Blueprint exam certification, which are all our promises to ensure customer interests.

Scrum PSM-II Test Blueprint VCE dumps help you save time to clear exam.

Research indicates that the success of our highly-praised PSM-II Test Blueprint test questions owes to our endless efforts for the easily operated practice system. Most feedback received from our candidates tell the truth that our PSM-II Test Blueprint guide torrent implement good practices, systems as well as strengthen our ability to launch newer and more competitive products. Accompanying with our PSM-II Test Blueprint exam dumps, we educate our candidates with less complicated Q&A but more essential information, which in a way makes you acquire more knowledge and enhance your self-cultivation. And our PSM-II Test Blueprint exam dumps also add vivid examples and accurate charts to stimulate those exceptional cases you may be confronted with. You can rely on our PSM-II Test Blueprint test questions, and we’ll do the utmost to help you succeed.

The pass rate of our products increased last year because of its reliability. Our website provides the most up-to-date and accurate PSM-II Test Blueprint dumps torrent which are the best for passing certification test.

PSM-II PDF DEMO:

QUESTION NO: 1
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 2
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C

QUESTION NO: 3
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 4
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

QUESTION NO: 5
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C

Adobe AD0-E134 - Secondly, you can free download the demos to check the quality, and you will be surprised to find we have a high pass rate as 98% to 100%. We provide our candidates with valid Huawei H13-334_V1.0 vce dumps and the most reliable pass guide for the certification exam. So you can choose the version of ACFE CFE training quiz according to your personal preference. Our training materials can help you learn about the knowledge points of SAP C-THR96-2405 exam collection and improve your technical problem-solving skills. Huawei H14-331_V1.0 - When you apply for a job you could have more opportunities than others.

Updated: May 27, 2022