PSM-II Questions Vce & Scrum Exam PSM-II Score - Professional Scrum Master Level Ii PSM-II - Omgzlook

If you want to get a comprehensive idea about our real PSM-II Questions Vce study materials. It is convenient for you to download the free demo, all you need to do is just to find the “Download for free” item, and you will find there are three kinds of versions of PSM-II Questions Vce learning guide for you to choose from namely, PDF Version Demo, PC Test Engine and Online Test Engine, you can choose to download any one version of our PSM-II Questions Vce exam questions as you like. They will accurately and quickly provide you with Scrum certification PSM-II Questions Vce exam materials and timely update Scrum PSM-II Questions Vce exam certification exam practice questions and answers and binding. Besides, Omgzlook also got a high reputation in many certification industry. We would like to extend our sincere appreciation for you to browse our website, and we will never let you down.

Professional Scrum Master PSM-II So try to trust us.

Professional Scrum Master PSM-II Questions Vce - Professional Scrum Master level II (PSM II) You spend lots of time on these reviewing materials you don't know whether it is useful to you, rather than experiencing the service Omgzlook provides for you. Our windows software and online test engine of the PSM-II Exam Training exam questions are suitable for all age groups. At the same time, our operation system is durable and powerful.

Many times getting a right method is important and more efficient than spending too much time and money in vain. Our Omgzlook team devote themselves to studying the best methods to help you pass PSM-II Questions Vce exam certification. From the time when you decide whether to purchase our PSM-II Questions Vce exam software or not, we have provided you with comprehensive guarantees, including free demo download before buying, payment guarantee in purchase process, one-year free update service after you purchased PSM-II Questions Vce exam software, and full refund guarantee of dump cost if you fail PSM-II Questions Vce exam certification, which are all our promises to ensure customer interests.

Scrum PSM-II Questions Vce VCE dumps help you save time to clear exam.

Research indicates that the success of our highly-praised PSM-II Questions Vce test questions owes to our endless efforts for the easily operated practice system. Most feedback received from our candidates tell the truth that our PSM-II Questions Vce guide torrent implement good practices, systems as well as strengthen our ability to launch newer and more competitive products. Accompanying with our PSM-II Questions Vce exam dumps, we educate our candidates with less complicated Q&A but more essential information, which in a way makes you acquire more knowledge and enhance your self-cultivation. And our PSM-II Questions Vce exam dumps also add vivid examples and accurate charts to stimulate those exceptional cases you may be confronted with. You can rely on our PSM-II Questions Vce test questions, and we’ll do the utmost to help you succeed.

The pass rate of our products increased last year because of its reliability. Our website provides the most up-to-date and accurate PSM-II Questions Vce dumps torrent which are the best for passing certification test.

PSM-II PDF DEMO:

QUESTION NO: 1
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.

QUESTION NO: 2
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

QUESTION NO: 3
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 4
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
A. Ask the Development Team member to share the issue with the team as soon as possible.
B. Notify the test team.
C. Add a Product Backlog item to address the security issue.
D. Wait until the Sprint Retrospective to add security to the definition of "Done".
Answer: A
Explanation:
It is best to coach the Development Team members to collaborate on issues regardless of severity.
They may consult the Scrum Master of Product Owner if needed.

QUESTION NO: 5
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

Adobe AD0-E121 - Secondly, you can free download the demos to check the quality, and you will be surprised to find we have a high pass rate as 98% to 100%. We provide our candidates with valid SAP C-TS462-2022-KR vce dumps and the most reliable pass guide for the certification exam. Up to now we classify our HP HPE0-V27-KR exam questions as three different versions. Our training materials can help you learn about the knowledge points of Tableau TCC-C01 exam collection and improve your technical problem-solving skills. What is more, there is no interminable cover charge for our AACN CCRN-Adult practice engine priced with reasonable prices for your information.

Updated: May 27, 2022