PSM-II Interactive Ebook - Latest PSM-II Dumps Ppt & Professional Scrum Master Level Ii PSM-II - Omgzlook

Our company keeps pace with contemporary talent development and makes every learners fit in the needs of the society. Based on advanced technological capabilities, our PSM-II Interactive Ebook study materials are beneficial for the masses of customers. Our experts have plenty of experience in meeting the requirement of our customers and try to deliver satisfied PSM-II Interactive Ebook exam guides to them. Hence, if you need help to get certified, you are in the right place. Omgzlook offers the most comprehensive and updated braindumps for Scrum’s certifications. guide should be updated and send you the latest version.

Professional Scrum Master PSM-II It is your right time to make your mark.

Secondly, since our PSM-II - Professional Scrum Master level II (PSM II) Interactive Ebook training quiz appeared on the market, seldom do we have the cases of customer information disclosure. But our Examcollection PSM-II Dumps real exam is high efficient which can pass the Examcollection PSM-II Dumps exam during a week. To prevent you from promiscuous state, we arranged our Examcollection PSM-II Dumps learning materials with clear parts of knowledge.

The questions of our PSM-II Interactive Ebook guide questions are related to the latest and basic knowledge. What’s more, our PSM-II Interactive Ebook learning materials are committed to grasp the most knowledgeable points with the fewest problems. So 20-30 hours of study is enough for you to deal with the exam.

Scrum PSM-II Interactive Ebook - So our product is a good choice for you.

As to the rapid changes happened in this PSM-II Interactive Ebook exam, experts will fix them and we assure your PSM-II Interactive Ebook exam simulation you are looking at now are the newest version. Materials trends are not always easy to forecast on our study guide, but they have predictable pattern for them by ten-year experience who often accurately predict points of knowledge occurring in next PSM-II Interactive Ebook preparation materials.

And they are trained specially and professionlly to know every detail about our PSM-II Interactive Ebook learning prep. If you have never bought our PSM-II Interactive Ebook exam materials on the website before, we understand you may encounter many problems such as payment or downloading PSM-II Interactive Ebook practice quiz and so on, contact with us, we will be there.

PSM-II PDF DEMO:

QUESTION NO: 1
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C

QUESTION NO: 2
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 3
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C

QUESTION NO: 4
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 5
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

We have been always trying to make every effort to consolidate and keep a close relationship with customer by improving the quality of our CheckPoint 156-315.81 practice materials. Compared with the other products in the market, our Qlik QREP latest questions grasp of the core knowledge and key point of the real exam, the targeted and efficient Professional Scrum Master level II (PSM II) study training dumps guarantee our candidates to pass the test easily. Let us take a try of our amazing Cisco 200-301-KR exam questions and know the advantages first! You will find that you can receive our Cisco 500-490 training guide in just a few minutes, almost 5 to 10 minutes. Cisco 300-710 - And we have become a popular brand in this field.