PSM-II Questions & PSM-II Latest Exam Cram - Scrum Valid PSM-II Exam Answers - Omgzlook

And we will send you the new updates if our experts make them freely. On condition that you fail the exam after using our PSM-II Questions study guide unfortunately, we will switch other versions for you or give back full of your refund. All we do and the promises made are in your perspective. It is important to predicate the tendency of the PSM-II Questions study materials if you want to easily pass the exam. Now, all complicate tasks have been done by our experts. Omgzlook follows the career ethic of providing the first-class PSM-II Questions practice questions for you.

We can help you pass the Scrum PSM-II Questions exam smoothly.

They are time-tested PSM-II - Professional Scrum Master level II (PSM II) Questions learning materials, so they are classic. So that you will have the confidence to win the exam. Omgzlook's Scrum PSM-II New Test Collection Sheet exam training materials are highly targeted.

They have built a clear knowledge frame in their minds before they begin to compile the PSM-II Questions actual test guide. It is a long process to compilation. But they stick to work hard and never abandon.

Come and buy our Scrum PSM-II Questions exam guide!

If you are forced to pass exams and obtain certification by your manger, our PSM-II Questions original questions will be a good choice for you. Our products can help you clear exams at first shot. We promise that we provide you with best quality PSM-II Questions original questions and competitive prices. We offer 100% pass products with excellent service. We provide one year studying assist service and one year free updates downloading of Scrum PSM-II Questions exam questions. If you fail exam we support to exchange and full refund.

Up to now, many people have successfully passed the PSM-II Questions exam with our assistance. So you need to be brave enough to have a try.

PSM-II PDF DEMO:

QUESTION NO: 1
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

QUESTION NO: 2
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 3
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.

QUESTION NO: 4
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 5
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
A. Ask the Development Team member to share the issue with the team as soon as possible.
B. Notify the test team.
C. Add a Product Backlog item to address the security issue.
D. Wait until the Sprint Retrospective to add security to the definition of "Done".
Answer: A
Explanation:
It is best to coach the Development Team members to collaborate on issues regardless of severity.
They may consult the Scrum Master of Product Owner if needed.

With the help of our online version, you can not only practice our HP HPE0-V28 exam pdf in any electronic equipment, but also make you feel the atmosphere of HP HPE0-V28 actual test. And whenever our customers have any problems on our SAP E-S4CPE-2023 practice engine, our experts will help them solve them at the first time. Our valid Salesforce Public-Sector-Solutions practice questions are created according to the requirement of the certification center based on the real questions. SAP C-TS462-2023 - Also, we just pick out the most important knowledge to learn. Our SAP C_TS4CO_2023 training material comes with 100% money back guarantee to ensure the reliable and convenient shopping experience.