PSM-II Files - Scrum Reliable Test Professional Scrum Master Level Ii PSM-II Sample Online - Omgzlook

You just need to download the PDF version of our PSM-II Files exam prep, and then you will have the right to switch study materials on paper. We believe it will be more convenient for you to make notes. Our website is very secure and regular platform, you can be assured to download the version of our PSM-II Files study torrent. After you have successfully paid, you can immediately receive PSM-II Files test guide from our customer service staff, and then you can start learning immediately. Many students often start to study as the exam is approaching. Because our products will help you solve the problem, it will never let you down if you decide to purchase and practice our PSM-II Files latest question.

Professional Scrum Master PSM-II As for us, the customer is God.

Actually, just think of our PSM-II - Professional Scrum Master level II (PSM II) Files test prep as the best way to pass the exam is myopic. The inevitable trend is that knowledge is becoming worthy, and it explains why good Latest PSM-II Exam Pdf resources, services and data worth a good price. We always put our customers in the first place.

Our PSM-II Files preparation practice are highly targeted and have a high hit rate, there are a lot of learning skills and key points in the exam, even if your study time is very short, you can also improve your PSM-II Files exam scores very quickly. Even if you have a week foundation, I believe that you will get the certification by using our PSM-II Files study materials. We can claim that with our PSM-II Files practice engine for 20 to 30 hours, you will be ready to pass the exam with confidence.

Scrum PSM-II Files - You are the best and unique in the world.

As we enter into such a competitive world, the hardest part of standing out from the crowd is that your skills are recognized then you will fit into the large and diverse workforce. The PSM-II Files certification is the best proof of your ability. However, it’s not easy for those work officers who has less free time to prepare such an PSM-II Files exam. Here comes PSM-II Files exam materials which contain all of the valid PSM-II Files study questions. You will never worry about the PSM-II Files exam.

Not only we offer the best PSM-II Files training prep, but also our sincere and considerate attitude is praised by numerous of our customers. To cope with the fast growing market, we will always keep advancing and offer our clients the most refined technical expertise and excellent services about our PSM-II Files exam questions.

PSM-II PDF DEMO:

QUESTION NO: 1
An organization has just hired you as a new Scrum Master to help them transition their teams from their current traditional process to Scrum. The teams are currently structured to specialize in a single function. This is also known as component teams where a team would only address a single layer (i.e. design, frontend, backend, database, testing, etc.). You've introduced the concept of cross- functional teams where all the skills needed to produce business functionality, from end to end, are inside of a single team.
What should you keep in mind when transitioning from siloed teams to cross-functional teams?
(Choose two.)
A. It is easier to compare the performance between cross-functional teams in order to identify to which teams to assign tasks and which teams need additional coaching.
B. Without feature teams, you cannot do Scrum. Postpone Scrum adoption until the teams are reorganized in feature teams.
C. People from the different layers and components will need time to become accustomed to working and delivering unified functionality together as one Scrum Team thus productivity may suffer.
D. Newly formed teams will need time to stabilize before reaching their peak performance. During the initial stages of forming, performance will suffer and productivity may be low, although even then delivery of business value is still likely to increase.
Answer: C,D
Explanation:
Forming a team takes time, and members often go through recognizable stages as they change from being a collection of strangers to a united group with common goals. Bruce Tuckman's Forming,
Storming, Norming, and Performing model describes these stages. When you understand it, you can help your new team become effective more quickly.

QUESTION NO: 2
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
A. Ask the Development Team member to share the issue with the team as soon as possible.
B. Notify the test team.
C. Add a Product Backlog item to address the security issue.
D. Wait until the Sprint Retrospective to add security to the definition of "Done".
Answer: A
Explanation:
It is best to coach the Development Team members to collaborate on issues regardless of severity.
They may consult the Scrum Master of Product Owner if needed.

QUESTION NO: 3
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.

QUESTION NO: 4
What would be the main benefits of self-organization?
A. Increased creativity, self-accountability, commitment.
B. Increased rule compliance, self-accountability, commitment.
C. Increased capacity, accuracy of estimates, output.
D. Increased rule compliance, self-accountability, output.
Answer: A
Explanation:
Self-organized teams allow teams to creatively solve difficult problems, be accountable for the work they do, and commit to each other and the goals of the team.

QUESTION NO: 5
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

Our company committed all versions of Fortinet FCSS_ADA_AR-6.7 practice materials attached with free update service. You will come across almost all similar questions in the real EMC D-VXB-DY-A-24 exam. So prepared to be amazed by our EMC D-VXR-OE-23 learning guide! Salesforce CRM-Analytics-and-Einstein-Discovery-Consultant - So do not hesitate and hurry to buy our study materials. By analyzing the syllabus and new trend, our EMC D-NWG-DS-00 practice engine is totally in line with this exam for your reference.