P3 Latest Test Study Guide & Cima P3 Exam Material - Risk Management - Omgzlook

Our P3 Latest Test Study Guide study questions have simplified the complicated notions and add the instances, the stimulation and the diagrams to explain any hard-to-explain contents. Our P3 Latest Test Study Guide guide torrent is compiled by experts and approved by the experienced professionals. They are revised and updated according to the change of the syllabus and the latest development situation in the theory and practice. The services provided by our P3 Latest Test Study Guide test questions are quite specific and comprehensive. First of all, our test material comes from many experts. Actually, it is possible with our proper P3 Latest Test Study Guide learning materials.

CIMA Strategic Level Case Study Exam P3 Omgzlook can give you a brighter future.

Our company have the higher class operation system than other companies, so we can assure you that you can start to prepare for the P3 - Risk Management Latest Test Study Guide exam with our study materials in the shortest time. Then you no longer need to worry about being fired by your boss. The society has an abundance of capable people and there is a keen competition.

In fact, our P3 Latest Test Study Guide exam questions have helped tens of thousands of our customers successfully achieve their certification. The moment you choose to go with our P3 Latest Test Study Guide study materials, your dream will be more clearly presented to you. Next, through my introduction, I hope you can have a deeper understanding of our P3 Latest Test Study Guide learning quiz.

Now, quickly download CIMA P3 Latest Test Study Guide free demo for try.

Being anxious for the P3 Latest Test Study Guide exam ahead of you? Have a look of our P3 Latest Test Study Guide training engine please. Presiding over the line of our practice materials over ten years, our experts are proficient as elites who made our P3 Latest Test Study Guide learning questions, and it is their job to officiate the routines of offering help for you. All points are predominantly related with the exam ahead of you. You will find the exam is a piece of cake with the help of our P3 Latest Test Study Guide study materials.

P3 Latest Test Study Guide test engine can simulate the actual test during the preparation and record the wrong questions for our reviewing. You just need 20-30 hours for preparation and feel confident to face the P3 Latest Test Study Guide actual test.

P3 PDF DEMO:

QUESTION NO: 1
P Ltd manufactures and sells electrical goods through retail outlets.
N is P Ltd's Sales Director. He has been recently promoted from a senior sales position with
P Ltd. He has been forced to spend the first six months as Sales Director on dealing with an administrative mess left behind by the previous sales director.
You are a Senior Management Accountant at P Ltd. You have worked with N for many years.
N has worked hard and has made many changes that have brought significant benefit to the business.
N has asked you to postpone the recording of some purchase invoices so that he will meet his quarterly targets on profit margin.
What should you do?
A. Collect all the facts, distance yourself from the situation but say nothing.
B. Write up the facts of the issue and put it on your files.
C. Do nothing, no rules have been broken, tell N that you cannot do as he asks and that he needs to abide by the professional codes.
D. Document the situation and present the facts to your manager.
Answer: C

QUESTION NO: 2
M plc has a $2 million loan outstanding on which the interest rate is reset every 6 months for the following 6 months and the interest is payable at the end of that 6-month period. The next
6-monthly reset period starts in
3 months and the treasurer of M plc thinks that interest rates are likely to rise between now and then.
Current 6-month rates are 7.2% and the treasurer can get a rate of 7.7% for a 6-month forward rate agreement (FRA) starting in 3 months' time. By transacting an FRA the treasurer can lock in a rate today of 7.7%.
If interest rates are 8.5% in 3 months' time, what will the net amount payable be?
Give your answer to the nearest thousand dollars.
Answer:
$77000

QUESTION NO: 3
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C

QUESTION NO: 4
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C

QUESTION NO: 5
RFG is considering a major expansion that will result in a more diversified business model.
At present, RFG's market capitalisation is $240 million. This is based on a beta of 1.6. The risk free rate is 4% and the market rate of return is 9%. RFG is financed entirely by equity.
The company generates an annual cash surplus of $28.8 million.
The expansion will cost $50 million and will generate future cash flows of $12 million in perpetuity. This new business will reduce RFG's beta to 1.4.
Calculate the adjusted present value of the expansion.
A. $59 million
B. $321 million
C. $131 million
D. $81 million
Answer: D

And if you want to get all benefits like that, our ASQ CQE-KR training quiz is your rudimentary steps to begin. The more time you spend in the preparation for EMC D-ISM-FN-23 training materials, the higher possibility you will pass the exam. If you have bought the HP HPE0-S59 exam questions before, then you will know that we have free demos for you to download before your purchase. Salesforce Education-Cloud-Consultant - You must use it before the deadline day. By concluding quintessential points into IIBA ECBA actual exam, you can pass the exam with the least time while huge progress.