P3 Test Pdf - Cima Valid Risk Management Test Simulator Free - Omgzlook

There are different ways to achieve the same purpose, and it's determined by what way you choose. A lot of people want to pass CIMA certification P3 Test Pdf exam to let their job and life improve, but people participated in the CIMA certification P3 Test Pdf exam all knew that CIMA certification P3 Test Pdf exam is not very simple. In order to pass CIMA certification P3 Test Pdf exam some people spend a lot of valuable time and effort to prepare, but did not succeed. For the client the time is limited and very important and our product satisfies the client’s needs to download and use our P3 Test Pdf practice engine immediately. After the client pay successfully they could receive the mails about P3 Test Pdf guide questions our system sends by which you can download our test bank and use our study materials in 5-10 minutes. If you choose Omgzlook to provide you with the pertinence training, you can easily pass the CIMA certification P3 Test Pdf exam.

CIMA Strategic Level Case Study Exam P3 There is no point in regretting for the past.

CIMA Strategic Level Case Study Exam P3 Test Pdf - Risk Management If you master all key knowledge points, you get a wonderful score. There is no doubt that the certification has become more and more important for a lot of people, especial these people who are looking for a good job, and it has been a general trend. More and more workers have to spend a lot of time on meeting the challenge of gaining the P3 Real Exams certification by sitting for an exam.

Please totally trust the accuracy of questions and answers. Attending Omgzlook, you will have best exam dumps for the certification of P3 Test Pdf exam tests. We offer you the most accurate P3 Test Pdf exam answers that will be your key to pass the certification exam in your first try.

CIMA P3 Test Pdf - And your life will become better and better.

Our P3 Test Pdf practice dumps is high quality product revised by hundreds of experts according to the changes in the syllabus and the latest developments in theory and practice, it is focused and well-targeted, so that each student can complete the learning of important content in the shortest time. With P3 Test Pdf training prep, you only need to spend 20 to 30 hours of practice before you take the P3 Test Pdf exam.

We have faith in our professional team and our P3 Test Pdf study tool, and we also wish you trust us wholeheartedly. Our P3 Test Pdf test torrent keep a look out for new ways to help you approach challenges and succeed in passing the Risk Management exam.

P3 PDF DEMO:

QUESTION NO: 1
M plc has a $2 million loan outstanding on which the interest rate is reset every 6 months for the following 6 months and the interest is payable at the end of that 6-month period. The next
6-monthly reset period starts in
3 months and the treasurer of M plc thinks that interest rates are likely to rise between now and then.
Current 6-month rates are 7.2% and the treasurer can get a rate of 7.7% for a 6-month forward rate agreement (FRA) starting in 3 months' time. By transacting an FRA the treasurer can lock in a rate today of 7.7%.
If interest rates are 8.5% in 3 months' time, what will the net amount payable be?
Give your answer to the nearest thousand dollars.
Answer:
$77000

QUESTION NO: 2
P Ltd manufactures and sells electrical goods through retail outlets.
N is P Ltd's Sales Director. He has been recently promoted from a senior sales position with
P Ltd. He has been forced to spend the first six months as Sales Director on dealing with an administrative mess left behind by the previous sales director.
You are a Senior Management Accountant at P Ltd. You have worked with N for many years.
N has worked hard and has made many changes that have brought significant benefit to the business.
N has asked you to postpone the recording of some purchase invoices so that he will meet his quarterly targets on profit margin.
What should you do?
A. Collect all the facts, distance yourself from the situation but say nothing.
B. Write up the facts of the issue and put it on your files.
C. Do nothing, no rules have been broken, tell N that you cannot do as he asks and that he needs to abide by the professional codes.
D. Document the situation and present the facts to your manager.
Answer: C

QUESTION NO: 3
RFG is considering a major expansion that will result in a more diversified business model.
At present, RFG's market capitalisation is $240 million. This is based on a beta of 1.6. The risk free rate is 4% and the market rate of return is 9%. RFG is financed entirely by equity.
The company generates an annual cash surplus of $28.8 million.
The expansion will cost $50 million and will generate future cash flows of $12 million in perpetuity. This new business will reduce RFG's beta to 1.4.
Calculate the adjusted present value of the expansion.
A. $59 million
B. $321 million
C. $131 million
D. $81 million
Answer: D

QUESTION NO: 4
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C

QUESTION NO: 5
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C

ISACA CISA-CN - CIMA Certification exams are essential to move ahead, because being certified professional a well-off career would be in your hand. Our IBM C1000-137 study materials have the high pass rate as 98% to 100%, hope you can use it fully and pass the exam smoothly. We have organized a group of professionals to revise Dell D-AX-DY-A-00 preparation materials, according to the examination status and trend changes in the industry, tailor-made for the candidates. There is an irreplaceable trend that an increasingly amount of clients are picking up WGU Principles-of-Management study materials from tremendous practice materials in the market. Dell D-PWF-RDY-A-00 - So just come and have a try!