P3 Test Blueprint & P3 Most Reliable Test Questions - Cima P3 Exam Cram Review - Omgzlook

Up to now, our P3 Test Blueprint training quiz has helped countless candidates to obtain desired certificate. If you want to be one of them, please take a two-minute look at our P3 Test Blueprint real exam. And you can just visit our website to know its advantages. Also, our P3 Test Blueprint practice engine can greatly shorten your preparation time of the exam. So you just need our P3 Test Blueprint learning questions to help you get the certificate. Our P3 Test Blueprint exam questions have helped a large number of candidates pass the P3 Test Blueprint exam yet.

CIMA Strategic Level Case Study Exam P3 Do not lose hope.

CIMA Strategic Level Case Study Exam P3 Test Blueprint - Risk Management You can spend more time doing other things. our New P3 Exam Simulator Online study materials will also save your time and energy in well-targeted learning as we are going to make everything done in order that you can stay focused in learning our New P3 Exam Simulator Online study materials without worries behind. We are so honored and pleased to be able to read our detailed introduction and we will try our best to enable you a better understanding of our New P3 Exam Simulator Online study materials better.

As long as our P3 Test Blueprint learning material updated, users will receive the most recent information from our P3 Test Blueprint learning materials. So, buy our products immediately! To meet the needs of users, and to keep up with the trend of the examination outline, our products will provide customers with larest version of our products.

CIMA P3 Test Blueprint study materials are here waiting for you!

Are you an IT staff? Are you enroll in the most popular IT certification exams? If you tell me "yes", then I will tell you a good news that you're in luck. Omgzlook's CIMA P3 Test Blueprint exam training materials can help you 100% pass the exam. This is a real news. If you want to scale new heights in the IT industry, select Omgzlook please. Our training materials can help you pass the IT exams. And the materials we have are very cheap. Do not believe it, see it and then you will know.

Every day they are on duty to check for updates of P3 Test Blueprint study materials for providing timely application. We also welcome the suggestions from our customers, as long as our clients propose rationally.

P3 PDF DEMO:

QUESTION NO: 1
S Doc is an out-of-hours service provided by a country's government. The service allows members of the public to call and speak to a nurse who can advise on medical situations which are not obviously emergencies.
Depending on the situation the caller can be referred to the full emergency services, or be advised to go to Accident and Emergency at the nearest hospital. Alternatively, a callout from a general practitioner (GP) can be organised; the caller can be advised of where GP services are available; advice can be given over the phone; or a decision can be taken that no further action is required at least until normal services resume on the next working day.
There has been a suggestion that the nurses who take these calls could be replaced by suitably trained operatives who have available to them a specially designed expert system.
Which of the following are advantages of using an expert system instead of nurses?
A. The expert system will always follow the same path whereas the nurses may have more knowledge about some health issues and very little about others.
B. Some callers may present with complicated scenarios that a non-medically trained operative or expert system would be unable to recognise (for example, psychological issues).
C. The use of an expert system would ensure that only relevant questions were asked of the caller and that operatives did not miss something vital due to distraction or fatigue.
D. The operatives would be too careful and therefore would recommend unnecessary treatments or interventions.
E. Using an expert system would make operatives less inclined to feel sorry for the caller and ensure that only relevant facts were considered in coming to a decision.
Answer: A,C,E

QUESTION NO: 2
RFG is considering a major expansion that will result in a more diversified business model.
At present, RFG's market capitalisation is $240 million. This is based on a beta of 1.6. The risk free rate is 4% and the market rate of return is 9%. RFG is financed entirely by equity.
The company generates an annual cash surplus of $28.8 million.
The expansion will cost $50 million and will generate future cash flows of $12 million in perpetuity. This new business will reduce RFG's beta to 1.4.
Calculate the adjusted present value of the expansion.
A. $59 million
B. $321 million
C. $131 million
D. $81 million
Answer: D

QUESTION NO: 3
A project has an NPV of £1,200,000. The present value of material costs which are included in the NPV calculation are £8,000,000.
What is the sensitivity of the project to changes in material costs?
Give your answer to the nearest whole percentage.
Answer:
15%

QUESTION NO: 4
M plc has a $2 million loan outstanding on which the interest rate is reset every 6 months for the following 6 months and the interest is payable at the end of that 6-month period. The next
6-monthly reset period starts in
3 months and the treasurer of M plc thinks that interest rates are likely to rise between now and then.
Current 6-month rates are 7.2% and the treasurer can get a rate of 7.7% for a 6-month forward rate agreement (FRA) starting in 3 months' time. By transacting an FRA the treasurer can lock in a rate today of 7.7%.
If interest rates are 8.5% in 3 months' time, what will the net amount payable be?
Give your answer to the nearest thousand dollars.
Answer:
$77000

QUESTION NO: 5
P Ltd manufactures and sells electrical goods through retail outlets.
N is P Ltd's Sales Director. He has been recently promoted from a senior sales position with
P Ltd. He has been forced to spend the first six months as Sales Director on dealing with an administrative mess left behind by the previous sales director.
You are a Senior Management Accountant at P Ltd. You have worked with N for many years.
N has worked hard and has made many changes that have brought significant benefit to the business.
N has asked you to postpone the recording of some purchase invoices so that he will meet his quarterly targets on profit margin.
What should you do?
A. Collect all the facts, distance yourself from the situation but say nothing.
B. Write up the facts of the issue and put it on your files.
C. Do nothing, no rules have been broken, tell N that you cannot do as he asks and that he needs to abide by the professional codes.
D. Document the situation and present the facts to your manager.
Answer: C

SAP P_S4FIN_2023 - Everyone has their own life planning. Besides, the price of our Microsoft PL-400-KR learning guide is very favourable even the students can afford it. SAP C_THR81_2311 - It's better to hand-lit own light than look up to someone else's glory. Salesforce ADM-201 - And we are grimly determined and confident in helping you. Amazon ANS-C01 - Omgzlook present accomplishment results from practice of all candidates.