P3 Updates - Latest P3 Study Questions Download & Risk Management - Omgzlook

Our P3 Updates study materials are not only as reasonable priced as other makers, but also they are distinctly superior in the many respects. With tens of thousands of our loyal customers supporting us all the way, we believe we will do a better job in this career. More and more candidates will be benefited from our excellent P3 Updates training guide! But this is still not enough. In the IT industry, CIMA's P3 Updates exam certification is the essential certification of the IT industry. The last but not least we have professional groups providing guidance in terms of download and installment remotely.

CIMA Strategic Level Case Study Exam P3 Everyone has their own dreams.

Most of the experts have been studying in the professional field for many years and have accumulated much experience in our P3 - Risk Management Updates practice questions. Everyone has a utopian dream in own heart. Dreams of imaginary make people feel disheartened.

The job-hunters face huge pressure because most jobs require both working abilities and profound major knowledge. Passing P3 Updates exam can help you find the ideal job. If you buy our P3 Updates test prep you will pass the exam easily and successfully,and you will realize you dream to find an ideal job and earn a high income.

This is the royal road to pass CIMA P3 Updates exam.

P3 Updates practice materials are typically seen as the tools of reviving, practicing and remembering necessary exam questions for the exam, spending much time on them you may improve the chance of winning. However, our P3 Updates training materials can offer better condition than traditional practice materials and can be used effectively. We treat it as our major responsibility to offer help so our P3 Updates practice guide can provide so much help, the most typical one is their efficiency.

As to the cause, P3 Updates exam is a very important test. For IT staff, not having got the certificate has a bad effect on their job.

P3 PDF DEMO:

QUESTION NO: 1
The interest rate on EUR deposits is 7%. The interest rate on GBP deposits is 5%. The spot rate is EUR/GBP0.8500. What is the one year forward rate predicted to be assuming interest rate parity holds true?
A. 0.8662
B. 0.9633
C. 0.8341
D. 0.7500
Answer: C

QUESTION NO: 2
An oil company has entered into a joint venture with a competing oil company to develop a new oil field. The joint venture arrangement is intended to mitigate the risks associated with developing the oil field.
The following disclosure appears in the oil company's risk report:
"Many of our large projects and operations are conducted through joint ventures. These arrangements involve complex risk allocation and indemnification arrangements and we have less control over these activities than we would have if we had full ownership and control.
Our partners may have economic or business interests that are opposed to ours, and may exercise the right to block key decisions or actions. We believe the joint arrangement is in our best interest." Which of the following statements are correct?
A. Now the shareholders know the directors are aware of the risk.
B. The risk report says nothing useful about the risk.
C. If the risk report had not reported the risk the shareholders might not have been aware of the risk.
D. The shareholders now have more useful information.
E. The risk report means that the shareholders know exactly how bad the risk is.
Answer: A,C,D

QUESTION NO: 3
In relation to the use of the adjusted present value (APV) technique, which of the following statements are correct?
A. The weighted average cost of capital - net present value technique and the APV technique will, if applied correctly, give the same answer.
B. To apply APV, the proportions of debt and equity in the capital structure must be known.
C. The interest tax shield on the project's debt must be known, or at least estimated.
D. To apply APV the actual amounts of debt and equity in the capital structure must be known.
Answer: A,C

QUESTION NO: 4
M plc is an IT company that bids for large contracts to sell computer systems and also to service existing systems. M plc's senior management has always set budgets which are hard to achieve and have made no allowances for the recession.
The economy has improved and M plc's senior managers have made the budget even more optimistic. The budgeted sales target has been increased by 40%.
In the past, sales staff have not tried to achieve the budget sales because it was generally believed that the targets were impossible to reach.
M plc has recently appointed a new Sales Director who has decided that sales staff will be dismissed if they fail to meet sales targets for three successive months. He is also looking for higher sales margins than were achieved before.
What are the likely consequences of the new Sales Director's policy?
A. Sales staff will feel more settled and secure in their jobs.
B. Sales staff will tender for riskier contracts.
C. Sales staff will encroach on other sales staff territories to get more work.
D. Sales staff will be happier in their jobs.
E. Sales staff will look for new jobs.
Answer: B,C,E

QUESTION NO: 5
A UK based company is considering an investment of GB£1,000,000 in a project in the USA.
It is anticipated that the following cash flows will arise from this project.
The cash flows will be either US$400,000 with a probability of 40% or US$700,000 with a probability of 60% for each of the next three years; remitted to the UK at the end of each year.
Currently GB£1.00 is worth US$1.30.
The expected inflation rates in the two countries over the next four years are 2% in the UK and 4% in the US.
Applying the Purchasing Power Parity Theory, which of the following represents the expected net present value of the project in GP£ (to the nearest whole pound)?
A. GB£391,640
B. GB£554,047
C. GB£287,639
D. GB£(111,973)
Answer: C

Adobe AD0-E716 practice materials are highly popular in the market compared with other materials from competitors whether on the volume of sales or content as well. Our Omgzlook is the most reliable backing for every ISACA CRISC candidate. Microsoft AZ-500 - You only need several hours to learn and prepare for the exam every day. By by constantly improving our dumps, our strong technical team can finally take proud to tell you that our EMC D-AV-OE-23 exam materials will give you unexpected surprises. Blue Prism ROM2 - You can free download them to check if it is the exact one that you want.

Updated: May 27, 2022