P3 Format - Latest Study Guide P3 Free & Risk Management - Omgzlook

The CIMA P3 Format practice exam has the questions very similar to the actual exam, and all the P3 Format answers are checked and confirmed by our professional expert. Our P3 Format study pdf is especially designed to give you a unique experience and make sure your success pass. If you fail in the P3 Format actual test, we will give you full refund. If you have any confusion about our P3 Format exam questions, just contact us and we will help you out. We have hired professional staff to maintain P3 Format practice engine and our team of experts also constantly updates and renew the question bank according to changes in the syllabus. With the best quality and high accuracy, our P3 Format vce braindumps are the best study materials for the certification exam among the dumps vendors.

Come and buy our P3 Format exam questions!

The P3 - Risk Management Format certification exam training tools contains the latest studied materials of the exam supplied by IT experts. And after using our P3 Test Simulator Online learning prep, they all have marked change in personal capacity to deal with the P3 Test Simulator Online exam intellectually. The world is full of chicanery, but we are honest and professional in this area over ten years.

The industrious Omgzlook's IT experts through their own expertise and experience continuously produce the latest CIMA P3 Format training materials to facilitate IT professionals to pass the CIMA certification P3 Format exam. The certification of CIMA P3 Format more and more valuable in the IT area and a lot people use the products of Omgzlook to pass CIMA certification P3 Format exam. Through so many feedbacks of these products, our Omgzlook products prove to be trusted.

CIMA P3 Format - A bad situation can show special integrity.

With the help of our P3 Format study guide, you can adjust yourself to the exam speed and stay alert according to the time-keeper that we set on our P3 Format training materials. Therefore, you can trust on our P3 Format exam materials for this effective simulation function will eventually improve your efficiency and assist you to succeed in the P3 Format exam. And we believe you will pass the P3 Format exam just like the other people!

If a person is strong-willed, it is close at hand. I think you should be such a person.

P3 PDF DEMO:

QUESTION NO: 1
P Ltd manufactures and sells electrical goods through retail outlets.
N is P Ltd's Sales Director. He has been recently promoted from a senior sales position with
P Ltd. He has been forced to spend the first six months as Sales Director on dealing with an administrative mess left behind by the previous sales director.
You are a Senior Management Accountant at P Ltd. You have worked with N for many years.
N has worked hard and has made many changes that have brought significant benefit to the business.
N has asked you to postpone the recording of some purchase invoices so that he will meet his quarterly targets on profit margin.
What should you do?
A. Collect all the facts, distance yourself from the situation but say nothing.
B. Write up the facts of the issue and put it on your files.
C. Do nothing, no rules have been broken, tell N that you cannot do as he asks and that he needs to abide by the professional codes.
D. Document the situation and present the facts to your manager.
Answer: C

QUESTION NO: 2
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C

QUESTION NO: 3
M plc has a $2 million loan outstanding on which the interest rate is reset every 6 months for the following 6 months and the interest is payable at the end of that 6-month period. The next
6-monthly reset period starts in
3 months and the treasurer of M plc thinks that interest rates are likely to rise between now and then.
Current 6-month rates are 7.2% and the treasurer can get a rate of 7.7% for a 6-month forward rate agreement (FRA) starting in 3 months' time. By transacting an FRA the treasurer can lock in a rate today of 7.7%.
If interest rates are 8.5% in 3 months' time, what will the net amount payable be?
Give your answer to the nearest thousand dollars.
Answer:
$77000

QUESTION NO: 4
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C

QUESTION NO: 5
RFG is considering a major expansion that will result in a more diversified business model.
At present, RFG's market capitalisation is $240 million. This is based on a beta of 1.6. The risk free rate is 4% and the market rate of return is 9%. RFG is financed entirely by equity.
The company generates an annual cash surplus of $28.8 million.
The expansion will cost $50 million and will generate future cash flows of $12 million in perpetuity. This new business will reduce RFG's beta to 1.4.
Calculate the adjusted present value of the expansion.
A. $59 million
B. $321 million
C. $131 million
D. $81 million
Answer: D

So choosing our ISACA IT-Risk-Fundamentals training materials is a wise choice. The Open Group OGEA-103 - In order to successfully pass the exam, hurry up to visit Omgzlook to know more details. Considering your practical constraint and academic requirements of the EMC D-MSS-DS-23 exam preparation, you may choose the EMC D-MSS-DS-23 practice materials with following traits. IBM C1000-162 - In addition, if you first take the exam, you can use software version dumps. Microsoft MB-240 - Once you pay for it, we will send to you within 5-10 minutes.

Updated: May 27, 2022